QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 30 SEPTEMBER 2025
HIGHLIGHTS
• Shareholders overwhelmingly approved the formation of an unincorporated joint venture
(“Yangibana UJV” or “UJV”) with Wyloo Consolidated Investment Pty Ltd (“Wyloo”) for the Yangibana
Rare Earths and Niobium Project (“Yangibana Project”) at an Extraordinary General Meeting held on
30 July 2025.
• The UJV was formally completed on 21 September 2025, with Wyloo acquiring a 60% interest and
assuming management of the project. This partnership significantly de-risks the project’s
development and funding pathway.
• Completion of the Yangibana transaction resulted in the full cancellation of the Exchangeable Notes
first issued to Wyloo in October 2022 which had an outstanding value of $123 million including
accrued interest at completion date, eliminating all debt associated with the notes and materially
improving the Company’s capital structure.
• A successful visit to the US and Canada in September elevated the Company’s profile, validating
strong government and commercial support for Yangibana and generating significant investor
interest.
• On 21 August 2025, Hastings completed the acquisition of the Whiteheads gold project,
consolidating its gold portfolio.
• On 29 September 2025, the Company executed a binding agreement to sell its entire gold portfolio
to Metal Bank Ltd (ASX:MBK), sharpening Hastings’ focus as a pure-play rare earths and niobium
company.
• A confirmatory drilling program commenced at the Whiteheads Gold Project on 16 September 2025
(and completed on 4 October) to validate historical data ahead of the asset divestment.
Hastings Technology Metals Ltd (ASX:HAS) (“Hastings” or “the Company”), a key emerging supplier
of rare earth concentrate, is pleased to present its Quarterly Activities Report for the three-month period
ended 30 September 2025.
The quarter has been transformational for the Company, marked by the completion of the UJV, a
significant corporate transaction involving a plan underway to divest of its portfolio of gold assets to
shareholders, and continued progress in exploration and project development.
Page 2 of 8
CORPORATE & SUSTAINABILITY
Health and Safety
A Total Recordable Injury Frequency Rate of 0.00 was maintained for the quarter.
Environment
The quarter primarily comprised environmental statutory reporting and compliance activities. This
included ongoing environmental monitoring to comply with environmental approval commitments;
WWTP daily and quarterly monitoring, RO plant daily monitoring, production bore weekly monitoring,
monitoring bore monthly monitoring, dust quarterly monitoring, and rehabilitation monthly
photographic monitoring. Annual reporting was completed under the Mining Act 1978 and submitted to
the Mine Rehabilitation Fund (“MRF”) to comply with the 30 June reporting period. Ongoing activities
include statutory reporting, implementing on-site compliance monitoring and rehabilitation, regulatory
stakeholder dialogue, and supporting preparation for the next phase of site implementation.
OPERATIONS AND PROJECT DEVELOPMENT
Yangibana Rare Earths Project
The highlight of the quarter was the finalisation of the strategic UJV with Wyloo for the development of
the Yangibana Project. At the Extraordinary General Meeting held on 30 July 2025, shareholders
demonstrated strong support for the transaction, with all resolutions passed by an overwhelming
majority.
All conditions precedent for the completion of the transaction agreement between Hastings and Wyloo
and their related entities under the Transaction Agreement have been satisfied or waived. Accordingly,
a UJV has now been formed in respect of the Yangibana Project. Wyloo, which holds a 60% participating
interest, has been appointed Manager and Operator of the UJV, with Hastings retaining a 40%
participating interest.
This partnership brings Wyloo’s considerable technical and financial expertise to the project,
representing a pivotal step in de-risking the path to production and unlocking significant value for
Hastings’ shareholders. With the UJV now established, early works and detailed engineering activities are
progressing, with updated capital and operating cost estimates expected in the coming quarters.
NORTH AMERICAN STRATEGIC ENGAGEMENT
In September, Hastings’ management undertook a strategic engagement tour of North America
following the US government's firm intention to develop a non-China supply chain for rare earth to
magnets production. This initiative created new opportunities for the Yangibana Project not previously
encountered. This led to direct engagement with relevant senior government officials, as well as
commercial and financial stakeholders.
Austrade Critical Minerals Delegation – Washington DC & New York (14-19 September)
As part of a delegation led by Austrade, Hastings engaged in high-level meetings with senior officials
from the Trump Administration and key US departments responsible for critical minerals funding and
strategy. Key outcomes included:
• The US Government affirmed its strategy to secure rare earth elements supply from allied
nations like Australia to support its “America First” domestic manufacturing agenda.
Page 3 of 8
• Hastings received confirmation that major US companies (‘Primes’) are being actively directed to
secure their critical mineral supply chains from allied partners, supporting the commercial case
for Yangibana’s future production.
• Following a presentation to investors and financiers in New York, Hastings attracted a high level
of interest among the delegation, securing a dozen one-on-one meetings.
Rare Earth Mines & Magnets Summit – Toronto (22-24 September)
The Company participated in the Rare Earth Mines & Magnet Summit in Toronto, engaging with over 300
delegates from across the mine-to-OEM supply chain. The summit provided opportunities for numerous
discussions with potential end-users of Yangibana’s mixed rare earth carbonate.
The North American visit was highly successful in elevating the profile of Hastings and the Yangibana
Project within the western world’s critical minerals ecosystem. The tour validated strong US Government
and commercial support for the project, generated significant investor interest, and identified potential
downstream opportunities.
GOLD ASSETS DIVESTMENT
In line with its strategic focus on rare earths, the Company has actively managed its portfolio of gold
assets. On 21 August 2025, the Company completed the acquisition of the Whiteheads Gold Project, a
promising exploration tenure in the well-endowed gold region of Kalgoorlie in Western Australia.
Soon after the acquisition, on 16 September 2025, the Company commenced a ~1,500m drilling program
at the Whiteheads Project to confirm historical drilling results and define a maiden mineral resource.
The drilling was completed without incident on 4 October 2025, with samples now being assayed. The
maiden mineral resource is expected to be declared in November 2025.
In a significant corporate development, Hastings entered into a binding agreement with Metal Bank
Limited (ASX:MBK) (“MBK”) on 29 September 2025 to sell its entire portfolio of gold assets. These assets
include the Whiteheads Project, along with the Ark and Darcy gold tenements, each located in Western
Australia. This transaction will see Hastings vend its gold projects in exchange for shares in MBK,
providing the Company’s shareholders with direct exposure in the gold sector via an in specie distribution
of MBK shares at no cost. The transaction is subject to approval by shareholders at the Company’s
forthcoming Annual General Meeting to be held on 28 November 2025.
This divestment will allow Hastings to focus its resources on the world-class Yangibana Project and
Hastings’ wholly owned Brockman Heavy Rare Earths and Niobium Project (“Brockman Project”) .
EXPLORATION ACTIVITIES
During the quarter, exploration activities were primarily focused on the Whiteheads Gold Project. The
drilling program that commenced in September was designed to test the continuity and confirm the
grade of known gold mineralisation. The results of this program will be keenly anticipated as they will
inform the future exploration and development plans for these assets when it comes under the
ownership of MBK
Tim Gilbert, the Company’s Chief Operating Officer will be transferred to MBK as its Chief Executive
Officer upon completion of the sale of the gold assets.
Page 4 of 8
Figure 1 – Drill chip samples collected from the Seven Leaders prospect during the September 2025 drilling
program.
Figure 2 – Aerial view showing drill rigs and support team operating at the Seven Leaders prospect during the
September 2025 drilling program.
Page 5 of 8
EXCHANGEABLE NOTES
Full Cancellation of Exchangeable Notes
Completion of the Transaction Agreement with Wyloo resulted in the full and final settlement of the
outstanding $123 million Exchangeable Notes previously held by Wyloo, inclusive of accrued interest.
This transaction has significantly strengthened Hastings’ balance sheet by removing the entire debt
liability and associated interest obligations related to the Notes. The Company is now well positioned to
focus on its interest in the Yangibana Project and its wholly owned Brockman Project.
FINANCIAL POSITION
During the quarter, the Company had cash outflows on exploration and evaluation costs of $0.4 million,
for project development of $1.3 million and $0.15 million was paid in respect of directors’ fees, salaries,
and consulting fees. The Company had $0.8 million in cash and cash equivalents as of 30 September
2025.
Following the settlement of the Exchangeable Notes as explained above, the Company’s only remaining
loan facility is the $5.0 million senior unsecured Project Loan Notes facility with Equator Capital
Management Ltd, which matures in November 2029.
Post Quarter End
In October 2025, the Company sold its residual holding in Neo Performance Materials Inc, generating
sale proceeds of $14.6 million. This amount has been earmarked to settle the final cash payment of $7.4
million under the Transaction Agreement, which will be made within 45 days of commencement of the
UJV, completing all Transaction-related payments.
The Company also utilised its existing At-The-Market (ATM) facility by selling 3.15 million shares realising
an additional $2.1 million.
Authorised by the Board for release to the ASX.
FOR FURTHER INFORMATION CONTACT:
Charles Lew Vince Catania
Executive Chairman Chief Executive Officer
+65 6220 9220 +61 8 6117 6118
Page 6 of 8
ABOUT HASTINGS TECHNOLOGY METALS LIMITED
Hastings Technology Metals Limited is a Perth-based rare earths company focused on the development
of its flagship Yangibana Rare Earths and Niobium Project. Located in the Gascoyne region of Western
Australia, the Yangibana Project contains one of the most highly valued deposits of NdPr in the world
with an NdPr to Total Rare Earth Oxide ratio of up to 52% in some areas of the orebody.
With an initial mine life of 17 years, the Yangibana Project is expected to become a globally significant
source of NdPr, a critical component in the manufacture of permanent magnets used in advanced
technology products including electric vehicles, renewable energy, humanoid robotics, and digital
devices.
The Yangibana Project is fully permitted for immediate development and is well-timed to meet the
forecast supply gap for rare earth elements accelerated by the growth in electric vehicles and wind
turbines, both vital for the global energy transition. It will be developed in two stages with an initial focus
on the construction of the mine and beneficiation plant to produce 37,000 tonnes per annum1
of mixed
rare earth concentrate. Hastings recognises in its geological model and mine plan the potential for a
multi-commodity recovery process stream which underpins the economic recovery of rare earth
minerals and associated critical minerals like ferro-columbite, and hafnium-enriched zircon.
For more information, please visit www.hastingstechmetals.com
1
Hastings confirms that all material assumptions underpinning the Ore Reserves supporting the Life of Mine Plan in ASX release
dated 6 February 2023, forecast financial information and production targets in the ASX release dated 31 May 2023 and
supplemented by the 16 February 2024 ASX release continue to apply and have not materially changed. In addition, production
targets and forecast financial information are based on Ore Reserves and Mineral Resources (Measured and Indicated), and no
inferred mineral resources nor exploration target is included.
53
Brockman
Niobium and
HREE Project
100%
Ark Gold
100%
Stage1
Stage 2 – Hydromet JV
40% HAS, 60% Wyloo
Locations under consideration: Onslow, KSA
40% Hastings, 60% Wyloo
AUSTRALIA
WESTERN
AUSTRALIA
Darcys Gold Project
100%
Page 7 of 8
FORWARD LOOKING STATEMENTS
This release contains reference to certain intentions, expectations, future plans, strategies and prospects
of the Company. Those intentions, expectations, future plans, strategies, and prospects may or may not
be achieved. They are based on certain assumptions, which may not be met or on which views may differ
and may be affected by known and unknown risks. The performance and operations of the Company
may be influenced by a number of factors, many of which are outside the control of the Company. No
representation or warranty, express or implied, is made by the Company, or any of its directors, officers,
employees, advisers, or agents that any intentions, expectations, or plans will be achieved either totally
or partially or that any particular rate of return will be achieved.
Given the risks and uncertainties that may cause the Company’s actual future results, performance, or
achievements to be materially different from those expected, planned or intended, recipients should
not place undue reliance on these intentions, expectations, future plans, strategies and prospects. The
Company does not warrant or represent that the actual results, performance, or achievements will be
as expected, planned or intended.
The Company is under no obligation to, nor makes any undertaking to, update or revise such forward
looking statements, but believes they are fair and reasonable at the date of this release.
APPENDIX – MINING TENEMENTS HELD
YANGIBANA PROJECT
Tenement Locality Status Ownership
%
E09/2298 WA Live 100%
E09/1704 WA Live 100%
E09/2404 WA Live 100%
E09/2296 WA Live 40%
E09/1703 WA Live 40%
E09/1705 WA Live 40%
E09/1706 WA Live 40%
E09/2333 WA Live 40%
M09/0159 WA Live 40%
M09/0161 WA Live 40%
M09/0163 WA Live 40%
G09/0011 WA Live 40%
G09/0013 WA Live 40%
G09/0017 WA Live 40%
G09/0018 WA Live 40%
G09/0020 WA Live 40%
G09/0021 WA Live 40%
G09/0022 WA Live 40%
G09/0026 WA Live 40%
G09/0027 WA Live 40%
G09/0028 WA Live 40%
L09/0093 WA Live 40%
L09/0095 WA Live 40%
L09/0096 WA Live 40%
L09/0097 WA Live 40%
M09/0158 WA Live 40%
M09/0162 WA Live 40%
M09/0176 WA Live 40%
M09/0178 WA Live 40%
E09/1700 WA Live 40%
E09/1943 WA Live 40%
E09/1944 WA Live 40%
E09/2018 WA Live 40%
E09/1989 WA Live 40%
E09/2007 WA Live 40%
YANGIBANA PROJECT
Tenement Locality Status Ownership
%
E09/2084 WA Live 40%
E09/2086 WA Live 40%
E09/2095 WA Live 40%
E09/2129 WA Live 40%
E09/2137 WA Live 40%
E09/2334 WA Live 40%
E09/2364 WA Live 40%
E09/2403 WA Live 40%
G09/0010 WA Live 40%
G09/0014 WA Live 40%
G09/0023 WA Live 40%
G09/0024 WA Live 40%
G09/0025 WA Live 40%
G09/0029 WA Live 40%
L09/0066 WA Live 40%
L09/0067 WA Live 40%
L09/0068 WA Live 40%
L09/0069 WA Live 40%
L09/0070 WA Live 40%
L09/0071 WA Live 40%
L09/0072 WA Live 40%
L09/0074 WA Live 40%
L09/0075 WA Live 40%
L09/0080 WA Live 40%
L09/0081 WA Live 40%
L09/0082 WA Live 40%
L09/0083 WA Live 40%
L09/0085 WA Live 40%
L09/0086 WA Live 40%
L09/0087 WA Live 40%
L09/0089 WA Live 40%
L09/0091 WA Live 40%
M09/0157 WA Live 40%
M09/0179 WA Live 40%
BROCKMAN PROJECT
Tenement Locality Status Ownership
%
EA80/5248 WA Live 100%
P80/1626 WA Live 100%
P80/1628 WA Live 100%
P80/1629 WA Live 100%
P80/1630 WA Live 100%
ARK GOLD PROJECT
Tenement Locality Status Ownership
%
E09/2385 WA Live 100%
E09/2399 WA Live 100%
Rule 5.5
ASX Listing Rules Appendix 5B (01/12/19) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Hastings Technology Metals Ltd
ABN Quarter ended (“current quarter”)
43 122 911 399 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation (if expensed)
(b) development - -
(c) production - -
(d) staff costs (899) (899)
(e) administration and corporate costs (1,151) (1,151)
1.3 Dividends received (see note 3) - -
1.4 Interest received 14 14
1.5 Interest and other costs of finance paid (152) (152)
1.6 Net income taxes (paid)/recovered - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(2,188) (2,188)
2. Cash flows from investing activities
- -
2.1 Payments to acquire:
(a) entities
(b) tenements - -
(c) property, plant and equipment (1,256) (1,256)
(d) exploration & evaluation (if capitalised) (421) (421)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (01/12/19) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
2.2 Proceeds from the disposal of: -
-
-
-
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(1,677) (1,677)
3. Cash flows from financing activities
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3,909 3,909
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- -
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings (102) (102)
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other – Lease principal repayments (77) (77)
3.10 Other – Proceeds for shares not yet issued 200 200
3.11 Net cash from / (used in) financing
activities
3,930 3,930
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
688 688
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(2,188) (2,188)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(1,677) (1,677)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
3,930 3,930
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (01/12/19) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
753 753
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 753 490
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)*
753 490
*Post quarter end, the Company sold its holding in Neo Performance Materials Inc, generating total
cash inflows of $14.56 million of which $7.4 million will be paid to Wyloo as final payment per the
Transaction Agreement relating to the Yangibana Joint Venture. The Company also activated its
existing At-The-Market (ATM) facility by selling 3.15 million shares realising $2.13 million.
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
192
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of,
and an explanation for, such payments
Payments of director fees, company secretarial, and consultancy fees to directors and director-related
entities.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (01/12/19) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities 5,815 5,188
7.2 Credit standby arrangements - -
7.3 Other – Redeemable exchangeable notes - -
7.4 Total financing facilities 5,815 5,188
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
7.1 Loan facilities – In March 2025, Hastings Technology Metals Ltd organised additional insurance
premium funding of $456,639 to bring the total to $814,507 at 7.7% per annum. The premium funding,
held with Ledge Finance Ltd, is repayable in 12 equal monthly instalments with an end date of
September 2025 and February 2026 respectively.
In October 2024, Hastings Technology Metals Ltd entered into a $5,000,000 senior unsecured Project
Loan Notes facility with Equator Capital Management Ltd with the drawdown of loan notes and funds
settlement also completed in October 2024. The facility matures in November 2029.
7.3 Redeemable exchangeable notes - On 21 September 2025 the Company completed the formation
of the Yangibana Unincorporated Joint Venture in respect of the Yangibana Project. As part of
completion, all remaining Exchangeable Notes owing to Wyloo were cancelled, representing an early
repayment of debt in full ahead of the original maturity in October 2025. At the date of completion, the
Exchangeable Notes had a value of $123,259,272.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (Item 1.9) (2,188)
8.2 Capitalised exploration & evaluation (Item 2.1(d)) (421)
8.3 Total relevant outgoings (Item 8.1 + Item 8.2) (2,609)
8.4 Cash and cash equivalents at quarter end (Item 4.6) 753
8.5 Unused finance facilities available at quarter end (Item 7.5) -
8.6 Total available funding (Item 8.4 + Item 8.5) 753
8.7 Estimated quarters of funding available (Item 8.6 divided by
Item 8.3)
0.29
8.8 If Item 8.7 is less than 2 quarters, please provide answers to the following questions:
1. Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (01/12/19) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
Operating cash outflows are expected to decrease in the coming periods as the Yangibana
Project transitions into the joint venture structure with Wyloo. Under the terms of the
unincorporated joint venture, Wyloo will fund 60% of ongoing project expenditure,
substantially reducing Hastings’ direct funding requirement. As a result, operating cash
flows will reflect lower development spending by the Company, while still advancing the
project in line with schedule. In addition, recent divestments and capital inflows have
strengthened the Company’s liquidity position, supporting the continued progression of
activities at Yangibana without a material increase in net cash outflows.
2. Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Post quarter end, the Company sold off its holding in Neo Performance Materials Inc,
generating total cash inflows of $14.56 million. The Company also activated its existing At-
The-Market (ATM) facility, selling 3.15 million shares realising an additional $2.13 million.
The Company has 16.3 million options on issue with expiry date 1 May 2026. The options
are in the money and if exercised with an option exercise price of $0.50 would raise ~$8
million.
3. Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
The Company monitors its cash flow forecasts on a monthly basis to enable it to execute its
business plan. The Company has substantial assets and a demonstrated ability to
raise capital to fund its operations when required.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: ............................................
Authorised by: ............................................
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
31 October 2025
The Board
Share your feedback
Discover