Annual Report to shareholders
Released
Released
Announcement PDF
Yangibana Rare Earths
and Niobium Project
Annual Report
2024
Annual Report 2024
Contents
Acknowledgment of Country
Hastings Technology Metals acknowledges the Traditional Custodians
of Country and their connections to land, sea and community in the spirit
of cooperation and mutually beneficial objectives.
We pay our respect to their Elders, past and present, and extend that respect
to all Aboriginal and Torres Strait Islander peoples today.
We acknowledge the Traditional Custodians on the land in which we operate.
Corporate Information
Letter from the Chairman
02
Executive Leadership Team
06
Review of Operations
08
Environment, Social and Governance Review
12
Mineral resources and ore reserves statement
14
Tenement Schedule
21
Directors’ Report
24
Corporate Governance Statement
54
Auditor’s Independence Declaration
55
Consolidated Statement of Profit or Loss and Other Comprehensive Income
56
Consolidated Statement of Financial Position
57
Registered office
Bankers
Level 3, 5 Mill Street
National Australia Bank – Perth WA Australia
Consolidated Statement of Changes in Equity
58
Perth WA 6000
Westpac – Sydney NSW 2000 Australia
Consolidated Statement of Cash Flows
59
Auditors
Notes to the Financial Statements
60
Principal place of business
PricewaterhouseCoopers
Level 3, 5 Mill Street
125 St Georges Terrace
Consolidated Entity Disclosure Statement
93
Perth WA 6000 Australia
PERTH WA 6000
Directors’ Declaration
94
Mr Malcolm Randall
Share register
Website
Independent Auditor’s Report
95
Mr Jean Claude Steinmetz
Automic Group
www.hastingstechmetals.com
Additional Shareholder Information
99
ABN 43 122 911 399
Directors
Mr Charles Lew (Chairman)
Mr Guy Robertson
Mr Neil Hackett
Mr Bruce McFadzean
Joint Company Secretaries
Mr Guy Robertson
Mr Neil Hackett
Telephone: +61 (8) 6117 6118
Level 5, 191 St Georges Terrace
Perth WA 6000
Telephone: +61 1300 288 664
Securities Exchange
Australian Securities Exchange
ASX Code: HAS
Solicitors
King & Wood Mallesons – Perth WA Australia
Herbert Smith Freehills – Perth WA Australia
Annual Report 2024 | 1
Letter from the Chairman
Dear Fellow Shareholders,
With humility and gratitude, I present Hastings Technology
Metals Ltd’s (“Hastings” or the “Company”) Annual Report
for the financial year ended 30 June 2024, a year defined
by steady progress and strategic consolidation.
Throughout this period, we have made considerable
strides in advancing our flagship Yangibana Rare Earths
and Niobium Project (the “Project” or “Yangibana Project”),
bringing us ever closer to production. Along the way,
we have made some exciting discoveries, forged key
partnerships, driven down capital costs and laid a strong
foundation for the future. We also launched our new
Vision and Values where our people developed our culture
strategy, outlining behaviours critical towards achieving
our vision to become Australia's next rare earth producer.
These milestones have not only improved our prospects
but have also positioned Hastings to be a leading multicommodity mining company with a strong focus on the
rare earth magnets industry.
Advancing Yangibana
Yangibana is located in the remote Upper Gascoyne
region of Western Australia. Major developments were
achieved in this last financial year. With the unwavering
support of our shareholders to date, we have invested
$154 million in mine infrastructure and equipment
2 | Hastings Technology Metals
procurement. Our accomplishments include the
completion of the 298-bed Kurbilli accommodation
camp, a 1.8 km airstrip capable of landing 70-seater
planes, the construction of four water bores,
telecommunications towers, and over 20 kms of site
access roads. This substantial progress represents 32%
of the Project’s total capital cost, effectively de-risking
our capital expenditure and marking a significant
milestone in our journey towards production.
Four months ago, we proudly hosted a group of 50
investors, media, banks, research analysts, government
and key stakeholders for a site visit, showcasing the
infrastructure and progress at Yangibana. The positive
feedback received has reinforced our commitment to
delivering on our promises and staying focused on our
strategic goals.
In August 2023, we signed a fixed-price, fixed-schedule
Engineering, Procurement, and Construction (“EPC”)
contract valued at $210 million with GR Engineering
Services (“GRES”), one of the leading and wellestablished process engineering and contracting
companies in Western Australia. GRES has an enviable
track record and this contract, which includes a process
warranty, will further de-risk our path to production.
Reduced Capex
I would like to commend the Hastings’ management
team for achieving a significant cost reduction of $56
million following an in-depth cost review exercise.
The Project’s capital cost has been reduced to $474
million. With $154 million spent to date on the mine
site infrastructure, the remaining capital cost is $320
million, including $27 million for contingency.
Unlocking Additional Value
Recent geological findings have unlocked further
potential at Yangibana. Our Chief Geologist, Dr
Louis Schumann, revealed the relative simplicity and
economic viability of processing niobium concentrate
for sale from our rare earth tailings. Niobium, essential
for high-tech alloys in jet engines, steel beams and
girders for bridges and building construction also
possesses superconducting properties used in advanced
technology magnets for medical and material science.
We recently published an initial niobium resource estimate
based on historical drilling at Bald Hill and Simon’s Find.
Along with hafnium-rich zircon, the Yangibana Bald Hill and
Simon’s Find deposits show a well-balanced commodity
basket of high value. Further work is underway to bring
this into a reserve estimate in the next few months.
Additionally, exploration at Centipede Range
(approximately 50km from Bald Hill) revealed a high
concentration of heavy rare earths, where dysprosium
(Dy) and terbium (Tb) to total rare earth oxides ("TREO")
ratio of 11.8% ranks it high up on a global scale as a
valuable heavy rare earth oxides deposit.
Yangibana’s unique geology within the Gifford Creek
Ferro-carbonatite zone hosts an abundance of highgrade NdPr and critical metals, setting the foundation
for an expanded multi-commodity operation.
Our beneficiation plant design is suited for minor
modifications, enabling us to produce ferrocolumbite
niobium and hafnium-rich zircon at minimal additional
cost. As we progress, we will expand and define this
multi-commodity potential.
Importantly, Yangibana’s location and established
infrastructure positions us to accelerate our path in
establishing a multi commodity complex within a similar
timeframe as our rare earth concentrate production.
This is especially crucial as global supply chains
increasingly seek to diversify away from Brazil, which
currently provides 90% of the world’s niobium supply.
ESG and Community Engagement
This year’s report is reflective of Hastings maintaining
its Environmental and Social Governance ("ESG")
journey as a sustainable investment to realise the
potential of critical minerals in the role of a global shift
to low carbon technologies. We remain committed to
the UN Global Compact Ten Principles and Sustainable
Development Goals and continue communicating our
progress annually.
We continue to gauge our sustainability performance
using credible third-party rating agencies. We recognise
that this is a continuous process to report and uphold
our ESG commitments, which are integrally important
for our business and broader stakeholder community.
Annual Report 2024 | 3
Last October, Hastings and the Thiin-Mah, Warriyangka,
Tharrkari, and Jiwarli (“TMWTJ”) People jointly reaffirmed
our mutual commitment to working collaboratively to
develop the Yangibana Project following a review of
the first five-years of the Yangibana Rare Earths Project
Agreement (“the Agreement”).
TMWTJ leaders and elders met on-country with Hastings
to review the Agreement that was signed in November
2017. Collaborative discussions around employment,
training, business opportunities, and a review of
appropriate goals and targets with TMWTJ Senior Elder
Pop Peter Salmon, and the Implementation Committee,
ended with heritage site visits around Yangibana.
These were identified and protected as part of early
engagement between both parties.
Strengthening Strategic Partnerships
As part of our long-term vision of creating an integrated
mine-to-magnet supply chain, we were pleased to
announce a strategic investment of 9.8% in Hastings
by JL Mag Rare-Earth Co., Limited (“JL Mag”). As the
world’s largest producer of high-performance rare earth
permanent magnets, JL Mag’s involvement improves
our understanding of the permanent magnets demand
dynamics and, therefore, our ability to achieve our
mine-to-magnet ambitions, in combination with our
21.5% shareholding in Neo Performance Materials.
JL Mag is the world’s largest producer of highperformance rare earth permanent magnets and a
technology leader in the application of Grain Boundary
Diffusion. It has a prestigious global customer base
including many of the world’s top ten Electric Vehicle
manufacturers. It also has a leadership position in the
wind turbine generators and variable frequency airconditioner compressor markets.
Commercial Arrangements
Financial
We have extended our long-standing offtake agreement
with Thyssenkrupp to include rare earth concentrate
sales for two-thirds of our production in the first five
years, thereby ensuring bankability with lenders. This
arrangement is in addition to the binding offtake term
sheet signed in February with Baotou Skyrock Rare
Earth New Material Co. Ltd. (“Skyrock”) for 7 years and
for a minimum of 10,000 tonnes a year. In 2018, we
signed a contract with Skyrock to take our mixed rare
earth carbonate. However, when we decided last year
to de-couple our Project into two stages, with stage
one being the production of a rare earth concentrate,
Skyrock has now agreed to buy our concentrate and
self-manage the processing of our concentrate into rare
earth oxides, passing on the costs to Hastings for the
hydrometallurgy and oxides separation on a cost-plus
basis. This revised contracting model strongly supports
our mine economics and we have extended this
arrangement to the Thyssenkrupp contract.
To meet our interim funding needs, we undertook
a pro-rata renounceable rights issue in April. It was
partially underwritten by a few long-term shareholders
and myself. With the strong support of shareholders
we had a 72% take up and ended up raising $15.9
million. This enabled us to progress further with on-site
maintenance, ongoing engineering development, longlead equipment residual payments and working capital.
Although the rare earth sector has faced pricing
challenges over the past twelve to eighteen months,
we are now seeing signs of recovery, with a 10%
increase in NdPr oxide prices in the last month alone.
Market analysts forecast further price increases next
year, driven by a stronger consumer market and
lowered interest rates. As we look ahead, an anticipated
supply deficit in 2026 and beyond is expected to
shift market dynamics, leading to a supply-demand
imbalance. This environment will likely attract longterm thematic investors back into the rare earth and
magnets industry, strengthening our position as we aim
to come into production by the second half of 2026.
Whilst advancing the Project during the year with equity
funds, we have undertaken a comprehensive process
on various project debt funding pathways. During
the year, Hastings received several indicative project
funding proposals from multiple parties, including
from global mining funds, senior debt, and fixed
income investors (debt capital markets), to fund the
Yangibana Project in line with the target gearing ratio
of 60%. This is in addition to the previously announced
financing support from commercial banks and
government agencies. Hastings is assessing the terms
and conditions of various proposals and term sheets
to ensure it provides the right capital structure, cost of
capital and flexibility for the Company in the long-term
interest of shareholders.
Financiers are satisfied with the suite of updated lender
due diligence reports, including an Independent Technical
Expert Report by Behre Dolbear Australia (BDA), legal due
diligence reports and market report/ assessment. Leading
market consultant, CRU has assessed Yangibana to be
situated in the 1st quartile of the global rare earths margin
curve and is expected to be one of the highest margin
producers globally once in operation.
will deliver substantial economic benefits, including
royalties, taxes, and job creation, while also establishing
reliable and strategic rare earth supply chains for the
global market.
The future of Hastings is indeed bright. The progress
made over the past year brings us ever closer to realising
our ambition of becoming Australia's next rare earth
producer, encompassing not only neodymium and
praseodymium (“NdPr”) but also niobium. The coming
year will be pivotal as we continue to implement our
financing plans, define our niobium reserves, and
strengthen our management team in readiness for plant
construction and deliver the first production in 2H 2026.
Our core values of Passion, Teamwork, Tenacity and
Owners Mindset are underpinned by honesty, loyalty
and integrity. Our value system is the lamp that will
light our path as we continue in our journey to bring
Yangibana into production.
I would like to thank all our shareholders and
stakeholders for their unwavering support. Your belief
in Hastings has brought us this far and together we will
unlock the full potential of the extraordinary Yangibana
ore body that we have been gifted to steward and
realise its full potential. We look forward to bringing you
good news in the near future as we aim to get to Final
Investment Decision.
On behalf of the Board, I would like to extend my
heartfelt thanks to the entire Hastings team for their
unwavering hard work and dedication.
Yangibana is shovel-ready and fully permitted for first
production of rare earth concentrate in 2H 2026.
Closing Remarks
One dream, one team.
The Australian Government's "Future Made in Australia"
policy supports the critical minerals sector, further
strengthening our role in the global electrification and
renewable energy transition. The Yangibana Project
Warm regards,
Mr Charles Lew
Executive Chairman
4 | Hastings Technology Metals
Annual Report 2024 | 5
Executive Leadership Team
During the year, Hastings undertook an organisational restructure as part of ongoing
efforts to manage costs and fit with the current needs of the Company as it advances
financing and strategic options.
Accordingly, some executive and senior management roles were made redundant, which included the departure of
Chief Executive Officer, Paul Brown. Prior to Mr Brown’s appointment, Alwyn Vorster acted as Interim Chief Executive
Officer from November 2022 to July 2023.
With this change, the Executive Team structure was reduced to four members. Under the leadership of Charles Lew,
Executive Chairman and acting in the capacity of Chief Executive Officer, the other Executive Team members are Teck
Lim, Chief Financial Officer, Vince Catania, GM Corporate, and Tim Gilbert who was promoted to Chief Operating Officer.
Mr Charles Lew
Mr Teck Lim
Mr Tim Gilbert
Mr Vince Catania
Mr Lew took over Hastings in December 2013,
and early in 2014, he commissioned its first drill
programme for rare earth at Yangibana. Working
with two veteran geologists, they discovered this
unique ore body at Yangibana. Since then, Mr
Lew has invested significantly in the Yangibana
Project and led the company from exploration
all the way to being fully permitted and mine
infrastructure built and ready for construction of
the Beneficiation Plant.
Teck Lim is a chartered accountant with over
20 years’ accounting and finance experience,
specialising in mining and metals corporate
finance. He was the corporate finance lead to
Hastings whilst at KPMG Corporate Finance and
his corporate advisory and banking experience
include landmark critical minerals projects and
mega project financings in Australia and globally.
He has undertaken lead financing mandates for
Glencore, Gold Fields, BCI Minerals, Gold Road,
Aquila Resources and Rio Tinto.
Tim Gilbert was appointed Chief Operating Officer
in May 2024. He was previously Executive General
Manager Mining Operations, appointed in 2023,
after serving as General Manager Operations for
the Yangibana Project.
Vince Catania joined Hastings in 2023 as General
Manager Corporate Affairs and moved into his role
as GM Corporate in May 2024.
Prior to Hastings, Mr Lew spent more than 20 years
in investment banking in London and Singapore.
From 1996 to 2000, he was Managing Director
of ABN Amro Investment Bank in Singapore with
regional responsibilities for corporate finance and
mergers & acquisitions. After he left banking, he
started his own investment company, Equator
Capital which invested in private equity and
subsequently into trading in the futures market.
Mr Lim’s financing experience extends to
government agencies, multilaterals, commercial
banks, private equity, mining funds and bond
markets and he has worked with strategic
investors, joint venture development partners,
offtakers and commodity trading houses to
fund large scale mining projects from feasibility
studies through to commercial operations
and expansions.
Executive Chairman
Between 2004 and 2016, he was Independent
Non-Executive Director of three licensed financial
institutions subsidiaries of RHB Banking Group.
He also served on the Board of Singapore Medical
Group between 2007 to 2013.
He holds a BA (Hons) in Finance and Accounting
from the University of East London and a MSc
(MBA) in Management Science from Imperial
College, University of London.
6 | Hastings Technology Metals
Chief Financial Officer
Prior to joining Hastings, Mr Lim was Chief
Financial Officer at a nickel/cobalt company
and held various roles with ING Bank, HSBC
Bank and Deloitte within their resource industry
sectors. Teck holds a Bachelor of Commerce from
Murdoch University, a Certificate in Mining Studies
from the University of British Columbia, a Master
of Business Administration from the University
of Western Australia and is a graduate of the
Australian Institute of Company Directors (GAICD).
Chief Operating Officer
General Manager Corporate
He has responsibility for the Yangibana Project
including construction and future operations,
operational readiness, environmental approvals,
health and safety, and exploration.
A Member of the WA Parliament for 17 years
during which he represented the Gascoyne and
Pilbara regions of the State, he has extensive
experience in the development and execution of
public policy, and an excellent understanding of
stakeholder engagement.
Mr Gilbert is a mining engineer with more than
four decades of experience in a range of senior
roles in the resources sector across multiple
commodities, including battery and base metals,
diamonds and gold.
During his parliamentary career, Mr Catania held
senior roles in Government and Opposition, with
portfolios covering water, forestry, sport and
recreation, commerce, tourism, transport, and
Aboriginal affairs.
His expertise covers a range of strategic,
operational, construction and technical roles
for major contractors including Thiess, as
well as global mining companies including Rio
Tinto, Newmont and Gold Fields. Before joining
Hastings, he was General Manager of Covalent
Lithium’s Mount Holland Project.
Before retiring from politics, Mr Catania held the
vast seat of North West Central, which covers the
Gascoyne region in which Hasting’s Yangibana
Project is situated.
Mr Gilbert holds a Bachelor of Engineering in
Mining Engineering from the Camborne School
of Mines.
The combination of technical expertise and
practical multi-commodity project management
and oversight will enable him to deliver
the Yangibana Project for Hastings and
its shareholders.
His strong community-oriented approach enabled
him to secure substantial funding for regional
infrastructure projects.
He has exceptional State and Federal political
contacts, well established media contacts, a
detailed knowledge of government and agency
processes and an excellent understanding of the
community and stakeholder needs of the area.
Mr Catania’s affinity for the region he represented
is invaluable for Hastings as we continue to
develop our flagship Yangibana Project.
Annual Report 2024 | 7
Review Of Operations
Project Overview
Project delivery and capital review
Hastings is focused on the development of the
Company’s flagship Yangibana Project. Located 250kms
northeast of Carnarvon in Western Australia’s Upper
Gascoyne region, the project is located on Gifford
Creek Station which is part of Thiin-Mah Warriyangka
Tharrkari and Jiwarli country.
During the reporting period, the Company completed a
comprehensive review into the project delivery model
and capital cost, confirming the Yangibana Project
remains a world-class tier one project with excellent
project economics.
Company activities in FY24 were primarily focused
on cost reduction and consolidation as Hastings
moves into the next phase, the construction of the
beneficiation plant.
A key outcome of the review was the reduction in
capital costs, which were independently verified by
Behre Dolbear Australia.
The remaining capital cost for the Yangibana
Project reduced to $319 million (inclusive of $27
million in contingency).
Significant progress has been made to de-risk the
pathway to first concentrate production in 2026,
clearing the way for the project to advance further
towards main construction.
• Total Capital Cost $474 million
• Spent Capital Expenditure $154 million
(as at 30 June 2024)
• Remaining Capital Cost $319 million (including
contingency of $27 million)
A review of construction costs identified approximately
$30 million in savings, reflecting the increased maturity
of designs, further scope clarity around unawarded work
and the reduction of non-essential activities, including:
Development Activities
• A scope reduction in the EPC contract including the
amendment and optimisation of the crusher facility;
A total of $154 million has been spent on non-process
infrastructure and long-lead equipment for the
beneficiation plant.
• Reduction in management reserve due to the
optimisation and clarification of earthworks for the
processing plant;
• Removal of the Stage 2 hydrometallurgical plant
tailings storage facility;
• A review of site operating costs and a reforecast
of site services, owner’s costs, storage and
preservation have been updated to reflect the
latest timeline and estimates.
A further $26 million in savings were identified
across operating costs from a thorough review of the
processing plant commissioning and operating labour.
Savings in the mining package through optimised
scheduling, and a reduction in the scope of works for
Stage 2 (hydrometallurgical plant) of the Yangibana
Project, resulted in total savings of $56 million.
As at 30 June 2024, construction of the Yangibana
Project was 32% complete.
Long-lead equipment for the Yangibana Project
continued to arrive including the flotation cells and
storage silos.
Hastings has now acquired all long-lead time items with
items in storage and under preservation routine.
Items include the acid bake kiln, off-gas scrubbing plant,
SAG Mill, regrind mill, thickeners, flotation cells, storage
silos, and various other processing equipment.
For these long lead equipment packages, the majority
have completed payments and as such, forecast
cash outflows is expected to be reduced significantly
compared to historic spend until the main construction
works commences.
Yangibana – Updated Capital Cost Estimate
Capital cost
A$m
%
Processing Plant & NPI
201.0
43%
Enabling Works
114.1
24%
Subtotal – Direct Capital Cost
315.1
67%
Hastings Project Management
50.2
11%
Other Indirects
81.3
17%
Subtotal – Indirect Capital Cost
131.5
28%
Contingency/Reserve
26.9
5%
Total Capital Cost
473.5
100%
Incurred to 30-Jun-24
154.1
32%
Remaining (incl. contingency)
319.4
68%
5%
17%
43%
11%
24%
Processing Plant & NPI
Hastings Project Management
Contingency
Enabling works
Other Indirects
8 | Hastings Technology Metals
Annual Report 2024 | 9
Strategic Investment – JL Mag
It is the long-term vision of Hastings to pursue its
strategy of building a vertically integrated mine to
magnet company.
In July 2024, Hastings announced that the world’s
leading producer of rare earths permanent magnets,
JL Mag Rare-Earth Co., Limited (“JL Mag”), via its whollyowned subsidiary JL Mag Green Tech (Hong Kong)
Company Limited is to become a strategic investor.
Following completion of the $7.1 million strategic
investment (19.6 million shares at $0.36 per new
ordinary share), which is subject to customary overseas
direct investment approvals, JL Mag will own 9.8% of
the enlarged issued share capital of Hastings, and
Han Yu, Vice President of JL Mag, will join the Hastings’
Board. The placement price was at a 38.8% premium
to Hastings’ 30-day volume weighted average price
(“VWAP”) of $0.2593 and 22.8% premium to the 10-day
VWAP of $0.2932 up to and including 5 July 2024.
Hong Kong Stock Exchange listed JL Mag has a market
capitalisation of HK$16.4 billion/A$3.1 billion and is the
world’s number one producer of high-performance rare
earths permanent magnets by volume.
It is also widely acknowledged as the world leader in
the application of Grain Boundary Diffusion technology
for magnets.
It is open to Hastings to offer JL Mag to participate in
future capital raisings to maintain its 9.8% shareholding
(subject to regulatory and shareholder approvals).
10 | Hastings Technology Metals
Board placement – Neo
Performance Materials Inc.
Capital Raising – Renounceable
Rights Issue
In June 2024, Hastings announced that following
constructive engagement with Neo Performance Materials
Inc., Neo’s Board of Directors had determined to appoint
Hastings’ nominee, Dr John McGarva, as an independent
director. Dr McGarva was appointed on 22 July 2024.
In April 2024, Hastings successfully completed a
Renounceable Rights Issue, which raised $15.9 million
from existing shareholders and underwriters. As a
result of the Renounceable Rights Issue, the exchange
price for the exchangeable notes issued to Wyloo
Consolidated Investments Pty Ltd has been adjusted
from $5.50 per share to $4.91 per share pursuant to
the terms of the debt facility.
Hastings holds a 21.5% strategic shareholding in Neo,
a leading global rare earths oxide processing and
permanent magnets producer listed on the Toronto
Stock Exchange (“TSX”), with manufacturing and
downstream processing facilities located in Estonia,
Thailand and China.
This investment provides Hastings with a unique
opportunity to pursue its long-term vision of creating
a vertically integrated mine to magnet supply chain.
Dr McGarva is a seasoned leader in product
development and manufacturing, with experience
spanning healthcare, industrial, and consumer
electronics industries. His extensive international
experience includes leadership roles across Europe,
Southeast Asia, and China.
Dr McGarva recently retired as Head of Engineering at
Dyson, where he led the global design and engineering
team for the company’s entire haircare product line,
guiding teams in Singapore, the Philippines, and the UK.
Under his leadership, Dyson’s Haircare business
evolved from a single product to a significant business
unit. A key element of Dyson haircare products is the
integration of permanent magnets and this expertise
positions Dr McGarva to offer customer insights and
strategic direction to Neo.
Geology and exploration
The Yangibana Project hosts numerous near surface
“iron stone” occurrences which consist of iron oxides
and hydroxides and hosts the main rare earth mineral
monazite. These surface expressions of ore are altered
ferrocarbonatite intrusives situated along fault zones
which developed between the Lyons Creek Fault in the
south and the Bald Hill Lineament in the north. Other
modes of occurrence for “iron stone” intrusions have
been identified along the contacts of various older
granite intrusives.
The petrogenesis of this specific ore type is constantly
under review with reference to understanding
the potential of additional carbonatite-related
mineralisation. Since the first drill program at the
Yangibana Project in 2014, Hastings has continuously
grown its resources and reserves through ongoing
exploration and metallurgy test work.
Current resources and prospects represent
24.2km cumulative strike of the prospective
ironstone intrusions.
In October 2022, the Company successfully completed
an extensive drilling campaign along the eight-kilometre
long Bald Hill – Simon’s Find – Frasers deposit, which
resulted in an increase in current total JORC Resource
of 29.93Mt @ 0.93% TREO (0.32% Nd2O3+Pr6O11).
Due to its proximity to the proposed site of the process
plant, this trend is vital for the ore feed required upon
project commissioning.
Subsequently in February 2023, Hastings announced a
25% increase in its Proved and Probable Ore Reserves
to 20.93Mt @ 0.90% TREO (or 0.33% Nd2O3+Pr6O11),
based on drilling, assaying, and optimisation work from
the 2021-22 exploration program. This also reflects the
completion of the acquisition of the 30% Yangibana
joint venture interest from Cadence Minerals Plc
(announced on 25 January 2023).
This increase in Ore Reserve estimates allows Hastings
to plan for a mine operating life of at least 17 years
Share your feedback