Quarterly Activities Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
28 October 2015
SEPTEMBER 2015 QUARTERLY ACTIVITIES REPORT
Hastings Technology Metals Limited
ABN 43 122 911 399
ASX Code: Shares ‐ HAS
Level 25, 31 Market Street
Sydney NSW 2000
PO Box Q128 Queen Victoria
Building NSW 1220 Australia
Telephone: +61 2 8268 8689
Facsimile: +61 2 8268 8699
info@hastingstechmetals.com
Board
Charles Lew (Chairman)
Anthony Ho (Non‐Exec Director)
Malcolm Mason (Non‐Exec Director)
www.hastingstechmetals.com
HIGHLIGHTS
Major drilling programme completed and all assays received
Updated JORC Resource estimates undertaken establishing
Resource Category
Tonnes
%TREO
%Nd2O3-Eq
Indicated
8,126,000
1.07
0.46
Inferred
4,236,000
1.07
0.41
TOTAL
12,362,000
1.07
0.44
(for definitions see end of text)
containing:132,500 tonnes of TREO, including
33,900 tonnes of neodymium oxide
8,950 tonnes of praseodymium oxide
590 tonnes of dysprosium oxide, and
930 tonnes of europium oxide
Mining studies, metallurgical test work and environmental work
all progressing on schedule and budget
First three Mining Leases granted covering all main deposits
An Advanced Scoping Study to be prepared during the
December 2015 quarter
Introduction
Hastings Technology Metals Limited (ASX:HAS) has continued to
advance its Pre-Feasibility Study (PFS) for the Yangibana Rare Earths
Project in the Gascoyne Region of Western Australia. The major
drilling programme to test targets mainly within tenements held 100%
by the Company was completed and all assays have been
received.
Based on the Company’s 2014 and 2015 drilling programmes, new
JORC Resources estimates have now been competed that include
Indicated Resources at the Bald Hill South, Fraser’s and Yangibana
1
West deposits, each within tenements held 100% by the Company, and the Yangibana
North deposit that is within tenements held under the Yangibana – REM Joint Venture in
which Hastings holds a 70% interest. Other prospects within the Joint Venture have also
been re-estimated.
Other areas of the Pre-Feasibility Study (PFS) continue to progress with mining studies,
metallurgical test work, and environmental field work all active during the period.
Major progress was made during the quarter with the granting of three Mining Leases
covering the bulk of the defined JORC resources.
The Company is producing an Advanced Scoping Study report during the coming quarter
to provide updated information on the progress of the PFS.
2015 RC and Diamond Drilling
During the quarter the Company completed a major drilling programme with details
provided in Table 1. Figure 1 shows the location of all holes drilled within the Yangibana
Project to date.
Deposit/Prospect
Bald Hill
Frasers
Yangibana North
Yangibana West
Terry's Find
Yangibana South
Yangibana
Proposed Camp
Site
Totals
RC
111
51
9
58
2
8
9
RC/DD
1
0
0
0
0
0
0
DD
13
3
0
3
0
0
0
Total
125
54
9
61
2
8
9
RC (m)
4603
2176
221
1785
54
192
192
DD (m)
408.3
155.6
0
65.6
0
0
0
Total
5011.3
2331.6
221
1850.6
54
192
192
1
249
0
1
0
19
1
269
31
9254
0
629.5
31
9883.5
Table 1 – Yangibana Project, 2015 drilling statistics
2
Figure 1 – Yangibana Project, Showing Yangibana Deposits with JORC Resources and Drilled Prospects
Bald Hill South
Hastings completed reverse circulation and diamond drilling at the Bald Hill South deposit
during the quarter. Holes tested:
the main zone where ironstone crops out strongly and where previous exploration
was concentrated;
the northern extension based on narrow, discontinuous outcropping ironstone; and
an area 700m to the south of the main zone where outcropping ironstone had not
previously been tested.
Table 2 provides details of the best intersections achieved in the RC drilling.
3
BHRC
17
33
32
51
53
59
70
72
and
75
79
87
94
125
142
144
From
36
4
4
17
9
7
26
0
7
0
22
6
28
16
52
26
To
39
16
16
21
14
12
42
3
10
14
29
16
38
19
62
31
Interval
3
12
12
4
5
5
16
3
3
14
7
10
10
3
10
5
%TREO
1.89
0.70
0.69
2.11
1.98
1.91
1.24
2.05
1.75
3.11
1.23
0.82
0.78
1.92
1.62
2.04
%Nd2O3-Eq
1.03
0.42
0.43
1.30
0.91
0.90
0.61
1.12
1.00
1.78
0.72
0.52
0.43
1.15
0.59
1.08
Table 2 – Yangibana Project, Bald Hill South 2015 drilling best intersections
Figures 2 and 3 provide cross sections of the mineralisation in the northern portion of Bald Hill
South and indicate that the deposit remains strongly open to the west.
Figure 2 – Yangibana Project, Bald Hill South Section 7,356,150N showing mineralisation
strongly open to the west
4
Figure 3 – Yangibana Project, Bald Hill South Section 7,356,350N showing
mineralisation strongly open to the west
Figure 4 shows the distribution of the mineralisation at Bald Hill South as m%Nd2O3-Eq
accumulations, again showing the deposit to remain open to the west.
5
Figure 4 – Yangibana Project, Bald Hill South, contoured m%Nd2O3-Eq
accumulations indicating high grade zones within the overall deposit
Two RC holes were drilled on one section to test a small, northwest oriented ironstone
outcrop known as Terry’s Find, some 650m to the west of the westernmost hole at Bald Hill
South. These holes returned encouraging intersections of 3m (4-7m) at 1.58%TREO with
0.60%Nd2O3-Eq (BHRC152) and 3m (33-36m) at 0.80%TREO with 0.40%Nd2O3-Eq (BHRC153).
The outcrop appears to occur on a trend between Bald Hill South and the eastern end of
the main mineralised zone that extends from Kane’s Gossan, some 2.5km to the northwest,
right through to the western end of Yangibana West, a further 11km to the west.
Fourteen diamond holes were subsequently drilled at Bald Hill South to provide:
duplicate intersections of earlier RC holes;
more accurate geological information in the more complex southern portion of the
deposit; and
provide samples for the measurement of specific gravity.
The best intersections returned from each hole are shown in Table 3. Note that portions of
some holes were sent for comminution test work and assays from these intervals remain
outstanding.
6
BHDD
108
109
110
111
And
117
From
15.01
24.20
2.40
4.18
19.8
5.50
To
22.50
28.70
8.48
9.72
23.40
15.24
Interval
7.49
4.50
6.08
5.54
3.60
9.74
%TREO
0.96
1.87
1.25
1.68
1.79
1.00
%Nd2O3-Eq
0.66
1.18
0.70
0.83
0.93
0.63
Table 3 – Yangibana Project, Bald Hill South 2015 diamond drillholes, best intersections
Reverse circulation and diamond drilling infilled and extended Hastings’ 2014 drilling at the
Fraser’s deposit during the quarter. This drilling extended the main mineralisation to the
northeast where it becomes more shallow-dipping. RC drilling also tested new targets to
the southeast and north with encouraging intersections achieved.
Table 4 provides details of the better intersections returned from the RC drilling.
FRRC
12
16
17
18
19
21
22
23
50
57
59
61
From
83
66
8
60
11
5
25
13
51
26
51
70
To
92
70
17
66
15
11
36
19
58
32
53
74
Interval
9
4
9
6
4
6
11
6
7
6
2
4
%TREO
3.37
1.52
0.96
1.55
1.55
1.49
0.91
1.48
0.77
1.25
3.10
1.56
%Nd2O3-Eq
1.80
0.79
0.50
0.88
0.74
0.89
0.60
0.68
0.49
0.65
1.73
0.83
Table 4 – Yangibana Project, Fraser’s Deposit 2015 drilling best intersections
Figures 5 and 6 provide cross sections of the mineralisation at Fraser’s, both indicating that
mineralisation remains strongly open at depth.
7
Figure 5 – Yangibana Project, Fraser’s Deposit, Section near the centre
of the deposit showing mineralisation strongly open at depth
Figure 6 – Yangibana Project, Fraser’s Deposit, Section towards the north-eastern
part of the deposit showing mineralisation strongly open at depth
8
Figure 7 shows the distribution of the mineralisation at Fraser’s as m%Nd2O3-Eq
accumulations, again showing the deposit remains open at depth.
Figure 7 – Yangibana Project, Fraser’s, contoured m%Nd2O3-Eq accumulations at
the Main Deposit indicating high grade zones within the overall deposit
Three diamond holes were subsequently drilled at the Fraser’s deposit, duplicating earlier
RC holes and to provide measurements of specific gravity across the deposit.
The best intersections returned from these holes are shown in Table 5. Note that a portion
of hole FRDD65 was sent for comminution test work and assays from this interval remain
outstanding.
Hole No
(FRDD)
63
64#
65*
and*
From
To
Interval
%TREO
%Nd2O3-Eq
13.50
74.60
24.5
30.50
19.53
75.00
29.34
36.00
6.03
0.40
4.84
5.50
4.29
3.24
0.88
1.29
2.01
1.72
0.60
0.97
Table 5 – Yangibana Project, Fraser’s 2015 diamond drillholes, best intersections
# high core loss adjacent to reported interval
*incomplete intersection, sample removed for comminution tests
9
Yangibana West and Yangibana North
The Yangibana West and Yangibana North deposits are part of one continuous deposit
defined only by the tenement boundary between ground held 100% by Hastings
(Yangibana West) and ground held under the Yangibana – REM Joint Venture (Yangibana
North).
The Yangibana West target had received limited drilling in the 1980s. Hastings’ 2015 drilling
tested the zone westwards from the tenement boundary until the mineralisation passes
under glacial cover, a distance of 1,200 metres.
Best intersections from RC within the Yangibana West area are shown in Table 6.
YWRC
3
20
22
24
23
39
37
45
50
58
41
43
From
37
1
21
5
24
2
9
18
42
7
12
33
To
42
7
25
10
26
5
19
24
45
13
15
39
Int
5
6
4
5
2
3
10
6
3
6
3
6
%TREO
2.00
1.01
1.70
1.16
1.80
1.29
1.81
1.84
2.20
2.73
1.87
1.53
%Nd2O3-Eq
0.61
0.42
0.63
0.43
1.03
0.53
0.70
0.81
0.95
1.04
0.72
0.62
Table 6 - Yangibana Project – Yangibana West Best RC Drill Intersections 2015
Figures 8 and 9 provide cross sections of the mineralisation at Yangibana West showing the
deposit remaining open at depth. Figure 8 shows the westernmost section drilled to date,
indicating potential for the deposit to continue further west under glacial cover.
10
Figure 8 – Yangibana Project, Yangibana West Section at the western end
of the deposit as drilled to date showing mineralisation strongly open at depth
Figure 9 – Yangibana Project, Yangibana West, Section at the eastern end of
the resource showing mineralisation strongly open at depth
Figure 10 shows the distribution of the mineralisation at Yangibana West and Yangibana
North as m%Nd2O3-Eq accumulations, again showing the deposits remain open at depth,
with higher grade mineralisation clearly associated with shoots within the overall deposits.
11
Figure 10 – Yangibana Project, Yangibana West and Yangibana North, contoured m%Nd2O3-Eq
accumulations showing high grade zones within the overall deposit
Three diamond holes were drilled at the Yangibana West deposit, duplicating earlier RC
holes and providing measurements of specific gravity throughout the deposit. The best
intersections achieved from this drilling are provided in Table 7.
Hole No
59
60
61
From
20.75
9.12
4.40
To
24.30
15.20
10.20
Interval
3.55
6.08
5.80
%TREO
3.24
1.69
2.08
%Nd2O3-Eq
1.05
0.62
0.77
Table 7 – Yangibana Project, Yangibana West 2015 diamond drillholes, best intersections
At Yangibana North the recent drilling infilled a small gap in the Company’s previous
coverage. It confirmed that the mineralisation continues uninterrupted westwards to the
Yangibana West Mining Lease Application.
Best intersections from RC drilling within the Yangibana North area are shown in Table 8.
12
Hole
YWRC001
YWRC005
YBRC065
From
4
3
0
To
9
6
6
Int
5
3
6
%TREO
1.59
3.22
1.63
%Nd2O3-Eq
0.54
0.98
0.56
Table 8 - Yangibana Project – Yangibana North Best RC Drill Intersections 2015
Figures 11 and 12 provide cross sections of the mineralisation at Yangibana North and show
the deposit to remain strongly open at depth.
Figure 11 – Yangibana Project, Yangibana North, Section towards the west end
of the resource showing mineralisation strongly open at depth
13
Figure 12 – Yangibana Project, Yangibana North, Section near the centre of the resource
showing mineralisation strongly open at depth
These results indicate the potential for a continuous open pit to be established extending
from the western end of Yangibana West to the eastern end of Yangibana North, a distance
of 1.9km. Higher grade mineralisation is generally associated with outcropping ironstone
lenses. It is reasonable to extrapolate this control over the remaining 10km of discontinuously
outcropping ironstone to the eastern end of Kane’s Gossan deposit. This provides Hastings
with future targets for establishing higher grade zones of mineralisation within the expected
continuous mineralisation over this 12km strikelength.
Resources
New resource estimates based on Hastings’ drilling campaigns of 2014 and 2015 and
incorporating a dilution factor as recommended by the Company’s mining consultants,
Snowden, were estimated by Hastings’ geological consultant, CoxsRocks Pty Limited.
Total Resources are as shown in Table 9.
Resource Category
Tonnes
%TREO
%Nd2O3-Eq
Indicated
8,126,000
1.07
0.46
Inferred
4,236,000
1.07
0.41
TOTAL
12,362,000
1.07
0.44
Table 9 – Yangibana Project, JORC Resource Summary, September 2015
14
The total resources for the Yangibana Project are 12.36mt at 1.07% TREO, a significant
increase from the resource of 6.79mt at 1.52% TREO as estimated in November 2014. The
total resource contains approximately 132,500 tonnes of TREO including 33,900 tonnes of
Nd2O3, 8,950 tonnes of Pr2O3, 590 tonnes of Dy2O3 and 920 tonnes of Eu2O3.
Table 10 provides a breakdown of the resources into individual deposits.
DEPOSITS WITHIN TENEMENTS HELD
100% BY HASTINGS
Category
Total Indicated Resources
Total Inferred Resources
Total Resources
Indicated
Inferred
Ind+Inf
Bald Hill South
Fraser's
Yangibana West
Ind+Inf
Ind+Inf
Ind+Inf
DEPOSITS WITHIN JOINT VENTURE
HELD 70% BY HASTINGS
Category
% TREO
%Nd2O3Eq
5,407,568
1,671,914
7,079,482
0.88
0.78
0.85
0.44
0.39
0.43
4,134,274
1,170,678
1,774,530
7,079,482
0.79
0.77
1.07
0.43
0.43
0.41
% TREO
%Nd2O3Eq
Tonnes
Tonnes
Total Indicated Resources
Total Inferred Resources
Total Resources
Indicated
Inferred
Ind+Inf
2,718,269
2,561,906
5,280,175
1.46
1.26
1.36
0.50
0.42
0.46
Yangibana North
Gossan
Hook
Kanes Gossan
Lions Ear
Bald Hill North
Ind+Inf
Inferred
Inferred
Inferred
Inferred
Inferred
3,189,269
220,522
348,819
577,828
842,034
101,703
5,280,175
1.46
1.07
1.09
1.16
1.42
0.43
0.50
0.34
0.31
0.41
0.47
0.25
Table 10 – Yangibana Project, September 2015 JORC Resources
15
Pre-Feasibility Study – Other Areas
Mining studies are in progress based on the geological interpretation and resource figures
as part of the PFS.
Metallurgical tests are progressing and a bulk sample from Bald Hill South and Fraser’s will
soon become available for hydrometallurgical and then separation test work.
Environmental studies are continuing with the second phase of the Fauna Survey
completed during the period with no areas of concern defined.
Mining Leases
During the quarter the first three Mining Leases were granted being M09/157 covering the
Bald Hill South deposit and the prospect 700m to the south (Hastings 100%); M09/158
covering the Fraser’s deposit and drilled targets to the north and south-west (Hastings 100%);
and M09/159 covering the Yangibana North deposit and the drilled prospects at Gossan,
Lion’s Ear, Hook, and Kane’s Gossan.
Corporate Matters
On 12 October 2015, shareholders at a general meeting voted to change the name of the
Company to Hastings Technology Metals Limited.
This change in name better reflects Hastings' emerging role in the supply of rare earths that
are critical in various products and technologies primarily in the fields of clean renewable
energy such as wind turbines, electric/hybrid electric vehicles, digital devices, consumer
electronics, healthcare, aerospace and defence.
* TREO is the sum of the oxides of the heavy rare earth elements (HREO) and the light rare
earth elements (LREO).
HREO is the sum of the oxides of the heavy rare earth elements europium (Eu), gadolinium
(Gd), terbium (Tb), dysprosium (Dy), holmium (Ho), erbium (Er), thulium (Tm), ytterbium (Yb),
lutetium (Lu), and yttrium (Y).
CREO is the sum of the oxides of neodymium (Nd), europium (Eu), terbium (Tb), dysprosium
(Dy), and yttrium (Y) that were classified by the US Department of Energy in 2011 to be in
critical short supply in the foreseeable future.
LREO is the sum of the oxides of the light rare earth elements lanthanum (La), cerium (Ce),
praseodymium (Pr), neodymium (Nd), and samarium (Sm).
16
** Neodymium Equivalence
Hastings is concentrating its efforts on the recovery of four important rare earths –
neodymium, praseodymium, dysprosium and europium. To portray the grade of the
mineralisation Hastings has established neodymium-equivalent figures where:The Nd2O3 equivalent (Nd2O3-Eq) values have been calculated based on the following rare
earths prices. These prices have been established by independent consultants Adamas
Intelligence and are being used by Hastings in the evaluation of the project.
Nd2O3 - US$85/kg
Pr2O3 – US$95/kg
Dy2O3 - US$550/kg and
Eu2O3 - US$635/kg
where Nd2O3-Eq =
((Nd2O3grade+((Pr2O3grade*(Pr2O3price/Nd2O3price))+(Dy2O3grade*(Dy2O3price/Nd2O3pri
ce))+ (Eu2O3grade*(Eu2O3price/Nd2O3price)))
such that Nd2O3 Eq = Nd2O3 + (1.1176 x Pr2O3) + (6.4706 xDy2O3) + (7.4706 xEu2O3)
About Hastings Rare Metals
Hastings Rare Metals is a leading Australian rare earths company, with two JORC
compliant rare earths projects in Western Australia.
The Yangibana Project hosts JORC Indicated and Inferred Resources totalling
12.36 million tonnes at 1.07% TREO, including 0.46% Nd2O3-Eq (comprising 8.13
million tonnes at 1.07% TREO Indicated Resources and 4.24 million tonnes at 1.07%
TREO in Inferred Resources).
The Brockman deposit contains JORC Indicated and Inferred Resources totalling
36.2 million tonnes (comprising 27.1mt Indicated Resources and 9.1mt Inferred
Resources) at 0.21% TREO, including 0.18% HREO, plus 0.89% ZrO₂ and 0.35% Nb₂O₅.
Rare earths are critical to a wide variety of current and new technologies,
including smart phones, hybrid cars, wind turbines and energy efficient light bulbs.
The Company aims to capitalise on the strong demand for critical rare earths
created by expanding new technologies. In late 2014 Hastings completed a
Scoping Study of the Yangibana Project that confirmed the economic viability of
the Project and in early 2015 commenced work on a Pre-Feasibility Study.
17
For further information please contact:
Andy Border, General Manager Exploration +61 2 8268 8689
Guy Robertson, Company Secretary +61 2 8268 8689
Competent Persons’ Statement
The information in this report that relates to Resources is based on information compiled
by Simon Coxhell. Simon Coxhell is a consultant to the Company and a member of the
Australasian Institute of Mining and Metallurgy. The information in this report that relates
to Exploration Results is based on information compiled by Andy Border, an employee
of the Company and a member of the Australasian Institute of Mining and Metallurgy.
Each has sufficient experience relevant to the styles of mineralisation and types of
deposits which are covered in this report and to the activity which they are undertaking
to qualify as a Competent Person as defined in the 2012 edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (“JORC
Code”). Each consents to the inclusion in this presentation of the matters based on his
information in the form and context in which it appears.
18
TENEMENT SCHEDULE as at 30 September 2015 (All tenements are in Western
Australia)
YANGIBANA PROJECT
YANGIBANA PROJECT
Hastings Rare Metals Limited
E09/2084
100%
E09/2086
100%
E09/2095
100%
E09/2129
100%
P09/482
100%
M09/157
100%
Yangibana Pty Limited (100% subsidiary)
E09/1700
100%
E09/1943, 1944
100%
E09/2018
100%
P09/467
100%
M09/158
100%
MLA09/162
100%
Gascoyne Metals Pty Limited (100%
subsidiary)
E09/1989
100%
E09/2007
100%
E09/2137
100%
E09/1043
70%
E09/1049
70%
E09/1703-06
70%
M09/159
70%
MLA09/160
100%
MLA09/161, 163
70%
MLA09/164, 165
100%
GLA09/10
100%
GLA09/11
70%
L09/66-74
100%
BROCKMAN PROJECT
Hastings Project Holdings Pty Limited (100%
subsidiary)
P80/1626-1635
100%
E80/4555
100%
EA80/4970
100%
19