31 May 2023
YANGIBANA PROJECT UPDATE
Staged development strategy to reduce project delivery risk
and enable faster pathway to cash flow
HIGHLIGHTS
•
Results of the project capital and delivery model review support a staged development strategy for the
Yangibana Rare Earths Project
•
This strategy will reduce upfront capital requirements and project execution risks as well as providing a
faster pathway to cash flow by Q1 2025
•
Initial focus will be on construction of the Yangibana mine and beneficiation plant to produce rare
earths concentrate (Stage 1), followed by development of a hydrometallurgical plant to produce mixed
rare earth carbonate (Stage 2)
•
Total project capital cost is now estimated at $948m, with the Stage 1 component being $470m (a 40%
increase to the estimate from 2020/21)
•
Fixed price contracting model aims to minimise risk of further capital cost increases, demonstrated by
the recent arrangement with GR Engineering for construction of the beneficiation plant
•
Beneficiation plant construction to commence in Q3 CY2023, supporting Stage 1 concentrate delivery
target date of Q1 CY2025
•
Concentrate offtake discussions underway with rare earth oxides producers in Australia and offshore
with a view to concluding firm contracts prior to drawdown of project finance debt in early 2024
•
Potential for strong Stage 1 financial returns with post-tax NPV11 of $538m, an IRR of 27.54% and average
annual EBITDA of $174m providing a funding source for Stage 2.
Hastings Executive Chair, Mr Charles Lew, said:
“The Yangibana Rare Earths Project is one of the world’s most advanced greenfield rare earth projects and
is well-timed to meet the forecast supply gap for magnet rare earth elements which are required to support
the global transition to clean energy.
“A comprehensive project review undertaken by our new experienced management team has confirmed
that this world-class project remains financially and operationally robust, with the investment in a Stage 1
mining and beneficiation plant being a compelling proposition.”
“The implementation of a two-stage development strategy for Yangibana will lower the upfront capital
funding requirements, reduce the project execution risk and enable a faster pathway to early project cash
flows which can be used to fund Stage 2 plant construction.”
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 1 of 6
Australia’s next rare earths producer, Hastings Technology Metals Ltd (ASX: HAS) (Hastings or the Company),
is pleased to provide an update on the outcomes of a review of the implementation plan for the Yangibana
Rare Earths Project (Yangibana) in Western Australia. The review commenced during Q1 CY2023 with the
objectives of mitigating scheduling and project execution risks and defining the capital cost for the
beneficiation plant and hydrometallurgy plant.
STAGED DEVELOPMENT STRATEGY
The key strategic outcome of the review is the staging of the development of the Yangibana mine and
beneficiation plant in the Gascoyne region, followed by the construction of the planned hydrometallurgical
plant at Onslow in the Pilbara region.
Hastings considers that a staged development of the Yangibana Project is the optimum strategy to allow the
production of first concentrate in Q1 CY2025 and a faster pathway to cash flow which can be used to support
funding of the hydrometallurgy plant.
Under the new strategy, the Yangibana Project will be developed in two stages:
•
Stage 1: Develop Yangibana mine and beneficiation plant to produce 37,000 tpa of rare earth
concentrate and achieve first concentrate on truck by Q1 CY2025
•
Stage 2: Develop Hydrometallurgy plant at Onslow to produce 15,000 tpa of Mixed Rare Earth
Carbonate (59% REO grade)
Construction for Stage 1 is expected to commence in Q3 CY2023 following the completion of early works
and site infrastructure currently at late stages of completion. The timing of the second stage development
will be determined after Stage 1 beneficiation plant has commenced.
UPDATED CAPITAL AND OPERATIONAL ESTIMATES
Reflecting the outcome of the project review, the capital estimate for Stage 1 and 2 of the Yangibana Project
is revised to $948m, which is an approximate 44% increase on a like-for-like basis to the estimates from
2020/21 (announced in February 2022). The increase reflects industry cost inflation, project scope
refinement and design growth and third-party imposed conditions. The estimated capital cost of $470m for
Stage 1 includes a contingency of $54m.
Taking into account capitalised operating expenditure, general and administrative costs, corporate costs,
operational readiness, holding costs for Onslow, capitalised interest and funding costs, the total funding
requirement for Stage 1 is $770m, of which $87m has been expended on early infrastructure works.
Table 1: Construction Phase Summary
Stage 1
Stage 2
Main construction start
Q3 2023
Q3 2026
Construction completion
Q4 2024
Q4 2027
Total capital costs
$470m
$478m
Capital costs incurred
$87m
1
$25m
1 Includes contingency
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 2 of 6
An approximate 30% increase in the estimated operational expenditure for Stage 1 is broadly in line with
market conditions, including labour and supply chain costs and price increases for the reagents required for
processing.
Table 2: Operations Summary
Stage 1
Stage 2
Life Of Mine (LoM)
17 years (Initial 3 years)
17 years (14 years from Stage 2)
Production start
Q1 2025
Q1 2028
Production end
Q1 2028 (Start of Stage 2)
Q3 2041
92,953t (Initial 3 years)
191,848t (14 years)
Contained TREO
25,097t (Initial 3 years)
113,190t (14 years)
Contained NdPr
10,295t (Initial 3 years)
39,702t (14 years)
Production
Stage 1 – Concentrate
Stage 2 – Mixed Rare Earth Carbonate
PROJECT ECONOMICS
The Stage 1 project delivers attractive forecast economic returns on a standalone basis, which will be further
enhanced by the future Stage 2 investment.
The pricing scenarios being considered for Stage 1 product include sales to Mixed Rare Earth Carbonate
producers via (i) China benchmark price (via Asian Metals published prices) or (ii) tolling arrangement or (iii)
profit sharing basis based on the producers’ realised oxides price. The current assumption for financial
modelling purposes is that a profit-sharing arrangement will apply, net-backed to cover both parties’ costs.
Table 3: Key Financial Metrics3
Post-tax NPV11 (ungeared)
Stage 1
(Standalone)
$538m
Stage 2
(from Stage 2 FID)
$1,018m
Post-tax IRR (ungeared)
27.54%
50.93%
Payback period
4.4 years
Net revenue (LOM)
$7,201m
Free cash flow (LOM)
$1,835m
$2,443m
Average EBITDA per annum
$174m
$251m
Further upside
on Stage 2 FID
2.1 years
$11,098m
3 Key Assumptions
REO price: Stage 1 (~US$24/kg assuming profit sharing model whereby HAS receives a price (real terms) of $18-28/kg).
Stage 2 (Blend of three Market Consultants’ forecasts including Wood Mackenzie, Adamas Intelligence and CRU (10-year average:
US$129/kg NdPr)
FX: A$/US$ 10-year (1st 10 years: 0.68), Forward curve thereafter (Bloomberg)
Discount Rate: Nominal, Post-Tax, 10.70% (equates to 8% real)
Valuation Dates: Stage 1 (1-Jul-23), Stage 2 FID (1-Jul-26)
NPV excludes >$100m sunk costs since Feb-22 (~$90m attributable to Stage 1 capital costs)
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 3 of 6
BASIS OF ESTIMATE
The updated capital cost estimate pricing was obtained in first quarter of 2023 and is in Australian dollars
(A$). The overall capital estimate has an estimated accuracy of -10/+15%. The operating cost estimate is
based on current industry rates for mining, labour costs for an owner operator model and updated market
pricing for reagents and consumables. It also includes factored allowances for maintenance and other
relevant costs.
CONTRACTOR DELIVERY MODEL
To give greater certainty to the capital estimate and delivery schedule, Hastings chose to adopt a fixed price
contract model which reduces overall project risk and limits further increases to the project’s capital cost.
In line with this strategy, the original Engineering, Procurement and Construction Management (EPCM)
model for the beneficiation plant was recently replaced with an Engineering, Procurement and Construction
(EPC) delivery model. This had the result of replacing approximately 260 separate Stage 1 construction
packages with a single, fixed price estimate with a single provider.
On 3 May 2023, Hastings announced it had entered into a binding EPC terms sheet with GR Engineering
(GRES) for the delivery of the Yangibana beneficiation plant and associated infrastructure.
The $210m contract is lower than cost estimates for an equivalent scope under the current EPCM model and
includes:
•
A fixed price component of $180m for the beneficiation plant; and
•
A provisional component of $30m, mainly for earthworks associated with the beneficiation plant
and tailings storage facility.
The EPC contract offers additional benefits and lowers risk in multiple areas, compared with the EPCM
model, including guarantees on time, cost and product quality with first concentrate delivery in Q1 CY2025.
YANGIBANA PROJECT UPDATE
Early infrastructure works at Yangibana are in the final stages, ahead of the commencement of main
construction in Q3 CY2023, including:
•
Kurrbili Accommodation Village: Stage 1 which includes the first 126 of 298 rooms, kitchen, messing
facilities, medical centre, administration buildings and gym will be ready for occupancy in May 2023
– 90% complete.
•
Yangibana Aerodrome: 2km landing strip completed – allowing for up to 70-seater aircraft, first
flight to Yangibana airstrip on 18 May 2023. Aerodrome buildings to be completed in August 2023.
•
SipHon borefield and pipeline: works are underway on water infrastructure, which will supply water
to the village, mine and construction works – 50% complete.
•
Site Access Road: Construction of ~25km access road alignment trafficable with two lanes to connect
with shire road network – 80% complete.
•
Communications: A series of communication towers installed to allow permanent high speed
communication with site – 100% complete.
•
Engineering design: progress achieved for the Yangibana beneficiation plant - 60% complete and
handed over to the new EPC contractor (GRES) for completion by August 2023.
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 4 of 6
NEXT STEPS
In addition to the early site works detailed above, a three-month early works agreement is now in place for
the beneficiation plant and infrastructure work, allowing GRES to immediately commence work on site,
ahead of the final agreement being finalised and the start of main construction in Q3 CY2023.
Hastings signed a binding offtake contract with Thyssenkrupp AG in April 2021 for up to two thirds of its
annual production volume4. To support the staged development strategy, concentrate offtake discussions
with rare earth oxides producers in Australia and offshore are underway with a view to concluding firm
contracts prior to drawdown of project finance debt.
Discussions to finalise the debt funding to support Stage 1 are well-advanced with lenders. NAIF’s Board has
approved a $220m loan facility for the Yangibana Project under a single stage combined beneficiation and
hydrometallurgical plants construction5. In addition, EFA has provided a letter of support to lend up to
$100m for the Project6. A letter of support for up to $50m in funding has been received from a major
international bank. Hastings is working with existing lenders and other financiers to finalise a project funding
package for Stage 1 by the end of September 2023.
This report has been approved by the Board for release to the ASX.
FOR FURTHER INFORMATION CONTACT:
Alwyn Vorster
Chief Executive Officer
+61 8 6117 8621
MEDIA QUERIES:
Stephanie Vanicek
Communications Manager
+61 405 183 237
4 See ASX Release ‘Hastings signs major offtake contract with thyssenkrupp Materials Trading GmbH’, dated 20 April 2021
5 See ASX Release ‘NAIF Increases Financial Support for Yangibana Rare Earths Project to A$220 million’, dated 17 January 2023
6 See ASX Release ‘Letter of Support secured from Export Finance Australia for $100m loan’, dated 21 March 2023
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 5 of 6
ABOUT HASTINGS TECHNOLOGY METALS LIMITED
Hastings Technology Metals Limited (ASX: HAS) is a Perth based rare earths company primed to become the
world’s next producer of neodymium and praseodymium concentrate (NdPr). NdPr are vital components in
the manufacture of permanent magnets used every day in advanced technology products ranging from
electric vehicles to wind turbines, robotics, medical applications, digital devices, etc.
Hastings’ flagship Yangibana Project (which comprises a mine and beneficiation plant at the Yangibana site,
and a hydrometallurgical plant at Onslow), in the Gascoyne and Pilbara regions of Western Australia,
contains one of the most highly valued NdPr deposits in the world with NdPr:TREO ratio of up to 52% in
some areas of the orebody. The Project is permitted for long-life production and with offtake commitments
signed and debt finance in advanced stage.
Hastings also owns and operates the Brockman project, Australia’s largest heavy rare earths deposit, near
Halls Creek in the Kimberley.
For further information on the Company and its projects visit www.hastingstechmetals.com
HASTINGS TECHNOLOGY METALS LIMITED
Level 3, 5 Mill Street, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 6 of 6
Australia’s Next Rare Earths Producer
Yangibana Rare Earths Project
Staged development strategy
Hastings Technology Metals Limited | ASX : HAS
31 May 2023
Importance notices and disclaimer
All currency amounts are in A$ unless stated otherwise
Disclaimer
This presentation has been prepared by Hastings Technology Metals Limited (“Company” or “Hastings”). This
presentation is not an offer, invitation, solicitation or other recommendation with respect to the subscription for,
purchase or sale of any securities in the Company. This presentation has been made available for information
purposes only and does not constitute a prospectus, short form prospectus, profile statement or offer information
statement nor does it constitute investment or financial product advice (nor taxation, accounting or legal advice)
and it is not intended to be used as a basis for making an investment decision.
This presentation is provided expressly on the basis that you will carry out your own independent inquiries into the
matters contained in the presentation and make your own independent decisions about the affairs, financial
position or prospects of the Company. The Company reserves the right to update, amend or supplement the
information at any time in its absolute discretion (without incurring any obligation to do so).
To the maximum extent permitted by law neither the Company, nor its related bodies corporate, officers, their
advisers, agents and employees accept any responsibility or liability to any person or entity as to the accuracy,
completeness or reasonableness of the information, statements, opinions or matters (express or implied) arising
out of, contained in or derived from this presentation or provided in connection with it, or any omission from this
presentation, nor as to the attainability of any estimates, forecasts or projections set out in this presentation. Any
such responsibility or liability is, to the maximum extent permitted by law, expressly disclaimed and
excluded. Nothing in this material should be construed as either an offer to sell or a solicitation of an offer to buy or
sell securities in the United States or any other jurisdiction where it would be illegal. It does not include all available
information and should not be used in isolation as a basis to invest in the Company.
Forward Looking Statements
This presentation contains reference to certain intentions, expectations, future plans, strategy and prospects of the
Company. Those intentions, expectations, future plans, strategy and prospects may or may not be achieved. They
are based on certain assumptions, which may not be met or on which views may differ and may be affected by
known and unknown risks. The performance and operations of the Company may be influenced by a number of
factors, many of which are outside the control of the Company. No representation or warranty, express or implied,
is made by the Company, or any of its directors, officers, employees, advisers or agents that any intentions,
expectations or plans will be achieved either totally or partially or that any particular rate of return will be achieved.
Given the risks and uncertainties that may cause the Company’s actual future results, performance or
achievements to be materially different from those expected, planned or intended, recipients should not place
undue reliance on these intentions, expectations, future plans, strategies and prospects. The Company does not
warrant or represent that the actual results, performance or achievements will be as expected, planned or
intended.
Corporate Presentation | Staged Development Strategy
The Company is under no obligation to, nor makes any undertaking to, update or revise such forward looking
statements, but believes they are fair and reasonable at the date of the presentation.
Competent Persons’ Statement
The information in this release that relates to Mineral Resources is based on information compiled by David
Princep and Lyn Widenbar. Both Mr. Princep and Mr Widenbar are independent consultants to the Company and
members of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr Princep and Mr Widenbar have
sufficient experience relevant to the styles of mineralisation and types of deposits which are covered in this
announcement and to the activity which they are undertaking to qualify as a Competent Person as defined in the
2012 edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’
(“JORC Code”).
The information in this announcement that relates to the Ore Reserves at Bald Hill, Simon’s Find, Fraser’s, Auer,
Auer North, Yangibana and Yangibana North is based on information reviewed or work undertaken by Mr. Stephen
O’Grady, member of the Australasian Institute of Mining and Metallurgy, and a Director of Intermine Engineering
Consultants. Mr O’Grady has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the preparation of mining studies to qualify as a Competent Person as defined by the JORC
Code 2012. Mr O’Grady consents to the inclusion in this announcement of the matters based on his information in
the form and context in which it appears.
The scientific and technical information in this announcement and that relates to process metallurgy is based on
information reviewed by Ms. Narelle Marriott (General Manager Process Development) of Hastings Technology
Metals Limited. Ms. Marriott is a member of the AusIMM and has sufficient experience relevant to the style of
mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a
Competent Person as defined by the JORC Code 2012. Ms. Marriott owns shares in the company and participates
in the company employee share plan. Ms. Marriott consents to the inclusion in this announcement of the matters
based on their information in the form and context in which it appears.
The information in this announcement that relates to Exploration Results in relation to the Yangibana Project is
based on information compiled by Mr. Andrew Ford BSc (Hons), a Competent Person, who is a member of the
Australian Institute of Mining and Metallurgy. Mr. Ford has sufficient experience that is relevant to the activity being
undertaken to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting
of Exploration Results, Minerals Resources and Ore Reserves. The Qualified Person has verified the data
disclosed in this release, including sampling, analytical and test data underlying the information contained in this
release. Mr. Ford consents to the inclusion in the announcement of the matters based on his information in the form
and context in which it appears.
2
Corporate overview
Developing the world-class Yangibana Rare Earths Project in Western Australia
Share price1
Shares on issue
$2.10 129.2m
Market capitalisation
$271m
HAS 12-month share price vs NdPr oxide price2
$150m
Key shareholders
160
Long-term NdPr Oxide Forecast3 140
5.00
120
4.00
100
3.00
80
60
2.00
40
1.00
20
May
2021
May
2022
$292m
Key assets
L1 Capital
11.8%
Yangibana Project
Western
Australia
Top 20 Shareholders
44.7%
Brockman Project
Western
Australia
5.5%
19.9% holding in
Neo Performance
Materials Inc
(TSX:NEO)
Canada
0
May
2023
Historical HAS Share Price (A$/sh)
NdPr oxide price US$/kg
180
6.00
A$/sh
$129m
Enterprise value
200
7.00
0.00
Cash at 30 April 2023
Exchangeable bonds
to Wyloo
NdPr Price (Historical)
NDPr Price (Blended Forecast)
Board and
Management
1 As at 26 May 2023
2 Asian Metal NdPr oxide ex-works price (daily) in RMB/kg converted to USD
3 Blended NdPr oxide long-term price forecast (Woodmac, CRU, Adamas Intelligence)
Corporate Presentation | Staged Development Strategy
3
Yangibana overview
Proven and de-risked flowsheet initially producing a concentrate, followed by a highvalue mixed rare earth carbonate to global market
Stage 2
Hydrometallurgical plant
Halls
Creek
Broome
Mining
20.9 Mt Ore Reserve
for 17-year mine life1
Beneficiation
Crushing, grinding,
flotation, tailings
& handling
Hydrometallurgy
Cracking, leaching,
precipitation
& drying
Port Hedland
Dampier
Onslow
Onslow Plant
Yangibana Mine Site
Carnarvon
~1.1 Mtpa to crusher
Traditional drill,
blast, load & haul
~37,000tpa
concentrate
(27% TREO)
15,000tpa Mixed Rare
Earth Carbonate
(59% TREO)
Meekatharra
Geraldton
Kalgoorlie
Perth
~3,400 tpa NdPr
Albany
Stage 1
Yangibana mine and
beneficiation plant
1 Refer ASX announcement “Yangibana Ore Reserves Increase by 25%”, dated 6 February 2023. Mine Life based on new Ore Reserve estimate.
Corporate Presentation | Staged Development Strategy
4
Staged development strategy
Staged development strategy
Enhanced two-stage delivery model supporting a de-risked pathway to becoming Australia’s next rare earths
producer by Q1 CY2025
Rare Earth Concentrate
Stage 1
Mixed Rare Earth
Carbonate
Stage 2
Downstream processing
Stage 3
Double production
Stage 1b
Double production at Yangibana
Yangibana mine and
beneficiation
Hydrometallurgical plant
• Fixed price EPC contact terms sheet
signed with GR Engineering
• Downstream processing providing
higher margins
• 19.9% ownership in Neo
Performance Materials
• Become a globally significant
Concentrate producer
• Reduces initial capital cost and
technical and execution risks
• Use Stage 1 free cash flows to fund
equity portion of Stage 2
• Complete scoping study in 2023
• Enabling a faster pathway to project
cashflows
• Secure additional debt for the
balance of funding required
• Opportunity to vertically align and
increase Hastings’ downstream
processing capacity
Mine to magnet strategy
• Consider mine gate purchasing from
other juniors
• Discussions ongoing with high
quality offtake partners
Short term - first concentrate
delivery in Q1 CY2025
Develop after Stage 1 reaches
practical completion
Corporate Presentation | Staged Development Strategy
Strategic plan for future growth and business sustainability
66
EPC delivery model reducing risk
Fixed price EPC contract for the beneficiation plant
GR Engineering
~$210m binding terms sheet entered
with final form contract to be completed
shortly
De-risks delivery
Offers additional benefits and lowers
risks in multiple areas compared to
previous EPCM model:
• Cost significantly lower
• Completion 3-months quicker
• Construction packages reduced
• Process and product quality
guarantees
Timeframe
Greater certainty with practical
completion by December 2024 and first
concentrate sale in Q1 CY2025
Corporate Presentation | Staged Development Strategy
7
Project execution schedule
Staged Development Strategy enabling a quicker and lower risk pathway to cashflow to support funding of Stage 2
Q1
2023
Q2
Q3
Q4
Q1
2024
Q2
Q3
Q4
Q1
2025
Q2
Q3
Q4
Q1
2026
Q2
Q3
Q4
Q1
2027
Q2
Q3
Q4
Q1
2028
Q2
Q3
Q4
Yangibana
EPC terms
agreed
Enabling Works
(Airstrip, Roads, Roads)
First
Concentrate
on Truck
Utilities & Services
(Power, Water, Gas)
Process Plant
Start of main
construction
Commission
Q3 2025 –
cashflow positive
Production Ramp Up to ~37ktpa (27% TREO
Concentrate)
Q2 2026 nameplate
Onslow
Enabling Works
Utilities & Services
(Power, Water, Gas)
Process Plant
Commissioning
Ramp Up to 15,000 tpa MREC
(59% TREO)
Q4 2028 nameplate
First MREC on Ship
Corporate Presentation | Staged Development Strategy
8
Staged construction and production metrics
Results of comprehensive project review to reduce overall project delivery risk
Stage 1
Stage 2
Yangibana mine and beneficiation plant
Hydrometallurgical plant
Main construction start
Q3 2023
Q3 2026
Construction completion
Q4 2024
Q4 2027
Total capital costs
$470m1
$478m
Capital costs incurred
$87m
$25m
17 years (Initial 3 years)
17 years (14 years from Stage 2)
Production start
Q1 2025
Q1 2028
Production end
Q1 2028 (start of Stage 2)
Q3 2041
Production
Stage 1 – Concentrate
Stage 2 – Mixed Rare Earth Carbonate
92,953t (Initial 3 years)
191,848t (14 years)
Contained TREO
25,097t (Initial 3 years)
113,190t (14 years)
Contained NdPr
10,295t (Initial 3 years)
39,702t (14 years)
CONSTRUCTION PHASE
OPERATIONS
Life of mine
Project capital cost
• Capital cost for Stage 1 and 2 of
$948m, representing a 44% increase
from 2020/21 estimates
• Phased into two stages to de-risk
project, generate early cash flow and
lower upfront funding requirement
• Significant advancement of early
infrastructure works reducing
remaining Stage 1 capital cost to
$383m (incl contingency)
• Stage 2 equity partially or completely
funded from Stage 1 concentrate
sales
Production
• Circa 8Ktpa TREO and 3Ktpa NdPr
for both Stage 1 and 2
• Total NdPr over LOM increased to
50Kt (from 43.3Kt in February
2022) due to mine life extension
from 15 to 17 years
Includes contingency
2 Capitalised operating expenditure, G&A, Corporate, Operational Readiness, Onslow holding costs, capitalised interest and funding costs
1
Corporate Presentation | Staged Development Strategy
9
Stage 1 capex estimates
Capital intensity per % NdPr produced remains competitive with other developers
Stage 1 capital cost (~A$470m)
Total Cost
(A$M)
Total Cost
(US$M)
%
Processing Plant (and NPI)
210
143
45
Enabling Works1
88
60
19
Subtotal - Direct Capital Cost
298
203
64
Hastings Project Mgt
58
40
12
Other Indirects2
59
40
13
Subtotal - Indirect Capital Cost
117
80
25
Contingency/Reserve
55
37
11
TOTAL Capital Cost
470
320
100
Incurred to date
87
57
19%
Remaining
383
252
81%
CAPEX
11%
13%
A$470m
45%
12%
19%
Processing Plant (GRES contract)
Enabling works
Hastings Project Mgt
Other indirects
Project cost review
Capex increases attributed to following
factors (broadly equally) to:
i.
Market inflation
ii. Design growth
iii. Third-party imposed conditions
Stage 1 capex
~40% increase from 2020/21 estimates
– new fixed price EPC delivery model
to reduce price escalation risk
Contingency
1Enabling works ($88m or 19%) represents: roads, aerodrome, village and borefields
2Other indirects ($59m or 13%) represents: fuel and accommodation, IT and comms, health and safety, consultants, insurances and other
Corporate Presentation | Staged Development Strategy
10
Operating expenditure competitive positioning
Opex intensity per % NdPr produced remains competitive with other developers
Stage 1 operating cost
8%
14%
Cost
US$/kg
REO
25.8
14
3.09
2.10
Power
14.9
8
1.79
1.22
Reagents and Consumables
26.1
14
3.12
2.12
Concentrate Transport
11.0
6
1.32
0.90
Tailings Transport
13.9
7
1.66
1.13
Other1
14.8
8
1.78
1.21
Contract Mining
63.5
33
7.59
5.16
Subtotal Direct cash cost
170.2
90
20.35
13.84
G&A
19.6
10
2.34
1.59
Total
189.8
100
22.69
15.43
Labour
Operating Costs
10%
8%
A$22.69/kg
14%
33%
6%
7%
Labour
Reagents and Consumables
Tailings Transport
G&A
%
Cost
A$/kg
REO
Total Cost
(A$M pa)
Power
Concentrate Transport
Contract Mining
Other
Stage 1 opex
~30% increase from 2020/21
estimates, largely due to labour, supply
chain bottlenecks and cost of reagents
Operational readiness
Inclusion of >$100m for capitalised
operation expenditure, G&A and
operational readiness
1Other represents: diesel consumption (3%), maintenance materials (2%), vehicle hire (2%), laboratory (1%)
Corporate Presentation | Staged Development Strategy
11
Revenue competitive positioning
High NdPr content in Concentrate and MREC support strong revenue assumptions
Yangibana revenue1
NdPr
3%
3%
Dy
Tb
Stage 1
LOM NdPr Content1
Strong offtake demand for Stage 1
Concentrate – discussions ongoing
Pricing scenarios for Concentrate
include sale to Mixed Rare Earth
Carbonate producers via:
i.
Asian Metal benchmark price
ii. Tolling arrangement
iii. Profit sharing based on their
realis
Share your feedback
Discover