FY23 Corporate Presentation - Year in Review
Released
Released
Announcement PDF
Australia’s Next Rare Earths Producer
Corporate Presentation
FY23 year in review
Picture: Kurrbili Village
Hastings Technology Metals Limited | ASX : HAS
FY23 year in review
|
1
5 October 2023
Importance notices and disclaimer
All currency amounts are in A$ unless stated otherwise
Disclaimer
This presentation has been prepared by Hastings Technology Metals Limited (“Company” or “Hastings”). This presentation
is not an offer, invitation, solicitation or other recommendation with respect to the subscription for, purchase or sale of any
securities in the Company. This presentation has been made available for information purposes only and does not
constitute a prospectus, short form prospectus, profile statement or offer information statement nor does it constitute
investment or financial product advice (nor taxation, accounting or legal advice) and it is not intended to be used as a basis
for making an investment decision.
This presentation is provided expressly on the basis that you will carry out your own independent inquiries into the matters
contained in the presentation and make your own independent decisions about the affairs, financial position or prospects of
the Company. The Company reserves the right to update, amend or supplement the information at any time in its absolute
discretion (without incurring any obligation to do so).
To the maximum extent permitted by law neither the Company, nor its related bodies corporate, officers, their advisers,
agents and employees accept any responsibility or liability to any person or entity as to the accuracy, completeness or
reasonableness of the information, statements, opinions or matters (express or implied) arising out of, contained in or
derived from this presentation or provided in connection with it, or any omission from this presentation, nor as to the
attainability of any estimates, forecasts or projections set out in this presentation. Any such responsibility or liability is, to the
maximum extent permitted by law, expressly disclaimed and excluded. Nothing in this material should be construed as
either an offer to sell or a solicitation of an offer to buy or sell securities in the United States or any other jurisdiction where
it would be illegal. It does not include all available information and should not be used in isolation as a basis to invest in the
Company.
Forward Looking Statements
This presentation contains reference to certain intentions, expectations, future plans, strategy and prospects of the
Company. Those intentions, expectations, future plans, strategy and prospects may or may not be achieved. They are
based on certain assumptions, which may not be met or on which views may differ and may be affected by known and
unknown risks. The performance and operations of the Company may be influenced by a number of factors, many of which
are outside the control of the Company. No representation or warranty, express or implied, is made by the Company, or
any of its directors, officers, employees, advisers or agents that any intentions, expectations or plans will be achieved either
totally or partially or that any particular rate of return will be achieved.
Competent Persons’ Statement
The information in this release that relates to Mineral Resources is based on information compiled by David Princep and
Lyn Widenbar. Both Mr. Princep and Mr Widenbar are independent consultants to the Company and members of the
Australasian Institute of Mining and Metallurgy (AusIMM). Mr Princep and Mr Widenbar have sufficient experience relevant
to the styles of mineralisation and types of deposits which are covered in this announcement and to the activity which they
are undertaking to qualify as a Competent Person as defined in the 2012 edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’ (“JORC Code”).
The information in this announcement that relates to the Ore Reserves at Bald Hill, Simon’s Find, Fraser’s, Auer, Auer
North, Yangibana and Yangibana North is based on information reviewed or work undertaken by Mr. Stephen O’Grady,
member of the Australasian Institute of Mining and Metallurgy, and a Director of Intermine Engineering Consultants. Mr
O’Grady has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the
preparation of mining studies to qualify as a Competent Person as defined by the JORC Code 2012. Mr O’Grady consents
to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.
The scientific and technical information in this announcement and that relates to process metallurgy is based on information
reviewed by Ms. Narelle Marriott (General Manager Process Development) of Hastings Technology Metals Limited. Ms.
Marriott is a member of the AusIMM and has sufficient experience relevant to the style of mineralisation and type of deposit
under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code
2012. Ms. Marriott owns shares in the company and participates in the company employee share plan. Ms. Marriott
consents to the inclusion in this announcement of the matters based on their information in the form and context in which it
appears.
The information in this announcement that relates to Exploration Results in relation to the Yangibana Project is based on
information compiled by Dr. Louis Schürmann (PhD), a Competent Person, who is a Fellow of the Australian Institute of
Mining and Metallurgy. Dr. Schürmann has sufficient experience that is relevant to the activity being undertaken to qualify
as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results,
Minerals Resources and Ore Reserves. The Qualified Person has verified the data disclosed in this release, including
sampling, analytical and test data underlying the information contained in this release. Dr. Schürmann consents to the
inclusion in the announcement of the matters based on his information in the form and context in which it appears.
Given the risks and uncertainties that may cause the Company’s actual future results, performance or achievements to be
materially different from those expected, planned or intended, recipients should not place undue reliance on these
intentions, expectations, future plans, strategies and prospects. The Company does not warrant or represent that the actual
results, performance or achievements will be as expected, planned or intended.
The Company is under no obligation to, nor makes any undertaking to, update or revise such forward looking statements,
but believes they are fair and reasonable at the date of the presentation.
FY23 year in review
|
2
FY23 year in review
FY23 year in review
|
3
Picture: Maiden flight landing at Yangibana Airstrip (18 May 2023)
A pivotal year
Significant progress made over the past 12 months to support pathway to first concentrate production
Q1
$110m capital raise via two
tranche placement and SPP
(underwritten)
$150m cornerstone
investment by Wyloo Metals
(Tattarang)
Mobilisation of contractors for
construction of airstrip and
village
Final results from 2021-22
resource definition RC drilling
program
Q2
Q3
Mineral Resource upgrade to
29.9Mt
Appointment of Teck Lim as
Chief Financial Officer
Acquisition of 19.9% Neo
Performance Materials Inc
(Neo) shareholding
NAIF increases financial support
to $220m
Offtake MOU signed with
Solvay (France)
Letter of support received from
Export Finance Australia for
$110m
25% increase in Ore Reserve
to 20.9Mt
Q4
$210m EPC contract for
beneficiation plant awarded to GR
Engineering Services (GRES)
Announcement of two-stage
development strategy for
Yangibana Project
Updated capital cost and
operational expenditure
Q1 FY24
Appointment of Paul Brown as
Chief Executive Officer
Expanded offtake with
thyssenkrupp (TK) to meet
bankability requirements
Successful completion of
financing due diligence including
Technical Report from Behre
Dolbear Australia (BDA)
Acquisition of Cadence’s 30%
interest in Yangibana JV
(Hastings now owns 100%)
FY23 year in review
|
4
1
FY23 financial summary
Early works completed to accelerate development of the Yangibana rare earths project in FY24
$260 million
$106 million
$150 million
Capital raised in FY23 – $110 million equity
raise and $150 million convertible note from
Wyloo
Invested in early infrastructure works at
Yangibana (at 30 June 2023) including
village, airstrip, borefield and access road
Invested in Neo to support Hastings’ mine to
magnet strategy
$102 million
$493 million
$315 million
Strong cash balance (at 30 June 2023)
Total assets – reflecting significant
advancement of infrastructure at Yangibana
1 Refer ASX announcement “Annual Report to Shareholders”, dated 28 September 2023
Net assets – reflecting significant value of
Hastings
FY23 year in review
|
5
Yangibana Project progress
All primary approvals in place and $106m already invested in early infrastructure works
Kurrbili Village – complete
294 beds, new admin building, mess, medical
centre and gym
SipHon Well Borefield – complete
30km pipeline; six bores
22% of Stage 1 capital cost already
spent on early infrastructure works
$52
$106
Stage 1 capital cost
$470m
$312
Yangibana Airstrip – complete
2km x 30m to support 70-seater aircrafts
First flight on 18 May 2023
Remaining capital cost
Aerodrome facilities - complete
Early infrastructure works
Contingency
FY23 year in review
|
6
1
FY23 cashflow movements
Significant investment into early infrastructure works at Yangibana and purchase of 20% shareholding in Neo
Early works/ infrastructure
- Village
- Airstrip
- Borefield
- Access Road
- LLT items
- Onslow costs
Purchase of 20%
in Neo
150.0
Wyloo
Funding
106.6
Equity
Raise
Dividends received:
from investment in
Neo
Opening cash
balance at
1 July 2022
Exploration costs:
updated Mineral Resource
and Ore Reserves in FY23
119.9
(120.5)
Opening cash
Net proceeds
(Share issue)
Payments for plant
and equipment
(151.0)
Proceeds from
borrowings
Payment for Neo
shares
2.5
(14.1)
Payments to
suppliers and
employees
Cash balance
at 30 June 2023
15.0
4.4
(6.8)
Dividends (Neo)
1 Refer ASX announcement “Annual Report to Shareholders”, dated 28 September 2023
Payments for
exploration
Net interest
Other
(7.2)
(0.2)
Payment of
borrowing costs
Lease payment /
exchange rate
(adj)
3.6
102.2
Bank guarantees
Closing cash
FY23 year in review
|
7
Project update
FY23 year in review
|
8
Yangibana Rare Earths Project
Positioning Hastings to become a significant supplier of critical minerals
needed to power the energy transition
Two stages
Ore Reserve – 20.9Mt
Mineral Resource – 29.9Mt
37,000 tpa
37% NdPr:TREO
Average ratio over mine life, including up to 52%
in some deposits
Halls
Creek
Broome
Port Hedland
17-year mine life
Stage 1 – Mine and beneficiation plant
Stage 2 – Hydrometallurgical plant
Stage 1 – concentrate production
Stage 2 – MREC production (15,000tpa)
Stage 2
Hydrometallurgical plant
Dampier
Onslow
Onslow plant
Yangibana mine site
Carnarvon
Meekatharra
Yangibana will produce ~3,400tpa of NdPr for use in rare earth magnets
55 million EVs
Carbon emissions by around 1.2
billion tonnes CO2e*
*compared to internal combustion engines
Geraldton
Kalgoorlie
170GW
Installed direct wind turbine
capacity
Perth
Stage 1
Yangibana mine and
beneficiation plant
Albany
FY23 year in review
|
9
1
Beneficiation plant EPC contract
Fixed-price contract for construction of beneficiation plant and associated infrastructure
$210 million contract
Engineering, Procurement and Construction
(EPC) contract with GR Engineering Services,
Including fixed price portion of $180 million
Lower cost
Compared to previous Engineering,
Procurement and Construction Management
(EPCM) model
De-risks project
Lowers project delivery risks, provides process
and product quality guarantees and greater
certainty on timeframe with first concentrate in
Q2 2025
1 Refer ASX announcement “Hastings Reduces Yangibana Delivery Risk Awards EPC Process Plant Contract to GR Engineering”, dated 3 May 2023
FY23 year in review
|
10
Stage 1 execution schedule
Enhanced staged development strategy enabling a quicker pathway to cashflow
Q1
2023
Q2
Q3
Q4
Q1
2024
Q2
Q3
Q4
Q1
2025
Q2
Q3
Q4
Q1
2026
Q2
Q3
Q4
EPC contract
executed
Enabling Works
(Airstrip, Roads, Village)
Start of main
construction
Utilities and services
(Power, Water, Gas)
First
concentrate
on truck
Q4 2025 –
cashflow
positive
Beneficiation Plant
Commissioning
Production Ramp Up to ~37ktpa
(27% TREO Concentrate)
Q2 2026 nameplate
FY23 year in review
|
11
Resource and Reserve development
Significant exploration targets providing growth optionality
Yangibana Project Mineral Resources and Ore Reserves1
Yangibana Project – total JORC Mineral Resources (30 Oct 22)1
60
Exploration target of
40 to 60 million tonnes2
40
Mt
%TREO
%Nd2O3+
Pr6O11
TREO
tonnes
Measured
4.97
0.96
0.37
47,721
Indicated
19.51
0.88
0.32
171,936
Sub-total
24.49
0.90
0.33
219,657
Inferred
5.45
1.05
0.31
57,298
TOTAL
29.93
0.93
0.32
276,955
Yangibana Project – total JORC Ore Reserves (6 Feb 23)1
30
17-year mine life
Million Tonnes
50
Category
20
10
0
Aug 2014
Oct 2015
Jun 2017
Mineral Resources
Jul 2018
Ore Reserves
Nov 2019
Feb 2023
Exploration Target
Deposit
Mt
%TREO
Bald Hill
8.12
0.79
0.32
41
Fraser’s
1.77
1.01
0.43
43
Simon’s Find
2.69
0.53
0.28
53
Auer
2.83
0.96
0.34
35
Yangibana
1.31
0.79
0.37
47
Yangibana North
4.21
1.29
0.34
26
TOTAL
20.93
0.90
0.33
37
1 Refer ASX announcement “Yangibana Ore Reserves Increase by 25%”, dated 6 February 2023 - numbers may not add due to rounding
2Refer ASX announcement “Potential identified to significantly expand Yangibana Resource base”, dated 15 December 2022
Disclaimer: There is no certainty that further exploration work will result in the determination of Mineral Resources (or Ore Reserves)
Nd2O3+
Pr6O11 as
% of TREO
%Nd2O3+
Pr6O11
FY23 year in review
|
12
Exploration potential
Only ~50sqkm drilled out compared to a total tenement area of ~650sqkm
66km strike length
Significant exploration upside with only one-third
of strike length (24km) defined as a Resource
Exploration focus
Expanding mine life beyond initial 17 years to
build long-term value for stakeholders
Existing 29.93Mt Mineral Resource has
been defined over 24km of strike length
Additional exploration potential strike
length of 42km identified
Disclaimer: There is no certainty that further exploration work will result in the determination of Mineral Resources (or Ore Reserves)
FY23 year in review
|
13
Financials, economics and ESG
FY23 year in review
|
14
1
Updated stage 1 metrics
Results of comprehensive project delivery and capital review in H1 2023
reaffirming attractive project economics
37,000 tpa
17 years
Life of mine
Production (stage 1 concentrate)
$470m
$106m
Stage 1 capital cost
Costs incurred (as at 30 June 2023)
$530m - $1,010m
27.5% - 50.9%
Post-tax NPV11 (ungeared)2
Post-tax IRR (ungeared)2
$175m - $250m
2.1 - 4.4 years
Average EBITDA per annum2
Payback period2
1 Refer ASX announcement “Corporate Presentation - Staged Development Strategy”, dated 31 May 2023
2 Higher project metric range shows the potential for improved economics through tolling and/or profit sharing arrangements
FY23 year in review
|
15
Corporate structure
Separate ring-fenced funding structures, with Wyloo convertible note secured over Neo shares
Hastings Technology
Metals Limited
(ASX: HAS)
100%
100%
Gascoyne Metals Pty
Ltd
100%
Yangibana Pty Ltd
Commentary
HTM Investments
(One) Pty Ltd
Convertible note security is over Neo
Performance Materials Inc. TSX
shares.
20.39%
Shareholding in
Neo Performance
Materials Inc.
(TSX: NEO)
Share security
• The Yangibana Project encompasses 100%
owned tenements through Yangibana Pty Ltd
and tenements owned 100% by Gascoyne
Metals Pty Ltd
• Investment in Neo and limited recourse
funding is ring fenced
Ring Fenced Yangibana Project
Funding Structure
Ring Fenced Neo Convertible Note
Structure
100%
Yangibana Rare
Earths Project
FY23 year in review
|
16
Basket price analysis
Based on market consultants and the expected Yangibana elemental composition
Elemental basket price (US$/kg TREO) (real $2023)
CRU, Adamas
Intelligence
69.5
27.01
1 Pricing includes 13% VAT and Opex includes US$10/kg processing charge
(excl. US$ 3/kg separation fee)
Market leading
basket
50
40
High value NdPr composition leads to
higher realised pricing
30
20
High margin
producer
10
0
Blend (Base Case)
2 year historical average
OPEX
Blend (Equity/High case)
2030
54.1
60
2029
Opex (LOM average)
CRU, Adamas
Intelligence, Wood
Mackenzie
2028
Blend (Equity/High Case)
48.1
2027
Blend (Base Case)
Actual
Up to 52% NdPr in TREO composition in
certain parts of the orebody
70
2026
2-year Historical Average
High NdPr:TREO
80
$US/kg TREO
US$/kg REO (Yangibana basket)
Market Consultant
2025
Elemental basket price
Yangibana Project will be in the first
quartile on the global margin curve
(assessed by CRU)
FY23 year in review
|
17
Concentrate and MREC offtake from thyssenkrupp
Offtake discussions focused on parties with existing hydrometallurgical facilities in Australia and Asia
Offtake contract for two-thirds of production
Counterparty
thyssenkrupp Materials Trading1
MREC : Heads of Agreement / MOU
Neo Performance Materials2
Solvay
Brussels, Belgium
Counterparty headquartered
Essen, Germany
Toronto, Canada
Agreement type
Binding Framework Agreement
towards take or pay offtake contract
Non-binding heads of agreement towards
offtake contract
Non-binding memorandum of understanding
towards offtake contract
Agreement term
10 years from production start
Initial period of 10 years
5 years (TBC)
Quantity
Years 1-5
Years 6-10
Stage 1 ~25,000tpa concentrate
Stage 2 ~10,000tpa MREC
2,500tpa MREC
~67% of production
~30% of production
(Processing in France)
Note: Hastings also has a non-binding master agreement with Schaeffler
1 Refer ASX announcement “Hastings and thyssenkrupp expand terms of offtake to align with Stage 1 of the Yangibana Rare Earths Project”, dated 12 September 2023
2 Refer ASX announcement “Hastings and Neo sign non-binding Heads of Agreement for rare earth concentrate offtake and downstream collaboration”, dated 13 June 2023
FY23 year in review
|
18
Funding update
Significant progress on funding pathway
Staged development
feasibility study
Completion of
independent due
diligence reports
Credit commitments
(Jan – May 2023)
(Jun – Sep 2023)
(Oct – Dec 2023)
Comprehensive project delivery
and capital review underpinning
move to staged development
strategy
Updated capital cost and operating
expenditure
De-risked project via shift to fixedprice EPC contracting structure
Completion of early infrastructure
works
Independent Technical Expert (ITE)
report by Behre Dolbear Australia
(BDA) confirming revised cost
estimates are reasonable and
appropriate
Market consultant report completed
by CRU, confirming Yangibana’s
competitive position in the first
quartile of global margin curve
Financing legal due diligence
reports completed by Herbert Smith
Freehills (HSF) and Gilbert + Tobin
Indicative commitments and term
sheets received from multiple
financiers
Financiers completing due
diligence and reviewing
confirmatory lender reports and
materials
Progress to finalise optimal debt
structure and funding stack by end
of CY2023
ESG ratings and sustainable
finance accreditation secured from
multiple agencies (Sustainalytics,
EcoVadis and DNV)
Updated offtake terms with
thyssenkrupp to meet bankability
requirements
Other customary financing
workstreams including tax and
financial modelling undertaken by
KPMG
FY23 year in review
|
19
Leading ESG credentials
Outperforming our peers and competitors in sustainability performance
Ranked fourth out of 159
companies in 2022 diversified
metals mining subindustry
category
Gold Rating – ranked in top five
per cent of companies assessed
Formal supporter of the
Task Force on Climate-Related
Financial Disclosures
Participant in the Ten Principles
of the UN Global Compact
Positively assessed against
IFC performance standards
and Equator Principles IV
(World Bank)
FY23 year in review
|
20
Mine to magnet strategy
FY23 year in review
|
21
Hastings mine-to-magnet strategy
Focused on the staged delivery of the Yangibana Project, with optionality to pursue mine-to-magnet business strategy
Stage 1
Mine and beneficiation plant
Stage 2
Hydromet plant
Stage 3
Mine to magnet strategy
Mining
Beneficiation
Hydrometallurgy
Oxide separation
RE metal creation
Alloy creation
Permanent magnets
Traditional drill,
blast, load and
haul
Crushing, grinding,
flotation, tailings
and handling
Cracking, leaching,
precipitation and
drying
Toll treatment,
separated high
purity RE oxide
precipitation
Separated RE
oxides turned
into RE metal
Create RE alloys
used in production
of permanent
magnets
Used for EVs, wind
turbines, electronic
appliances,
smartphones etc
Upstream
Downstream
FY23 year in review
|
22
Investment in TSX-listed Neo Performance Materials
20% strategic shareholding provides opportunity to create an integrated mine to magnet supply chain
Leading global manufacturer of
rare earth elements
• Owns the only operating commercial rare earth separation
facility in Europe, with additional facilities in China
• Rare earth metal, alloy and magnetic powder production
facilities in Thailand and China
• Rare earth magnet manufacturing facilities in China
• Sintered rare earth magnet manufacturing facility under
construction in Estonia, with production expected from 2025
A$379m
A$1.0bn
A$119m
A$2.5m
Market capitalisation
CY22 EBITDA
CY22 total revenue
Dividends paid to Hastings
from Neo shareholding in FY23
Picture: Groundbreaking ceremony for Neo’s sintered rare earth magnet manufacturing facility in Estonia
FY23 year in review
|
23
Investment highlights
Yangibana is positioned to supply neodymium and praseodymium needed for permanent magnets for the global
energy transition (EVs and wind turbines) and advanced technologies
World-class tier 1 asset
NdPr is critical to the global energy transition,
with significant supply deficit expected
Development ready
One of the highest compositions of
NdrPr:TREO ratios globally with a
life-of-mine average of 37% (up to 52%)
Fully permitted for first concentrate production;
$106 million already invested in early
infrastructure works
Enhanced delivery model
Robust project metrics
ESG focus
Two-stage development reducing
upfront capital requirements and faster
pathway to early project cashflows
Situated in first quartile on
global margin curve (CRU)
Leading ESG credentials; targeting
40-80% renewable energy for
Yangibana’s power supply
Strong market fundamentals
FY23 year in review
|
24
Appendix
FY23 year in review
|
25
Board of directors
Highly experienced and credentialed board
Charles Lew
Executive Chairman
• Took over HAS in December 2013 and appointed Chairman
• 30+ years investment banking experience in London and Singapore,
including as MD of ABN Amro Investment Bank Singapore and
independent non-executive director of Malaysia’s RHB Banking Group
• Entrepreneur with business experience in macro hedge fund, F&B and
real estate
Bruce McFadzean
Non-Executive Director
• Joined the Board in January 2021
• Managing Director of Sheffield Resources 2015 - 2021
• 40+ years in the global resource industry including 15+ years with BHP
Billiton & Rio Tinto
• Led successful financing and operation of mines around the world
Jean Claude Steinmetz
Non-Executive Director
• Joined the Board in July 2016
• Chief Operating Officer for Lynas Corporation 2013 - 2015
• 25+ years in the chemical industry with Rhodia and General Electric
• Chairman of the Auto Plastic and Innovative Materials Committee of
Sino-EU Chemical Manufacturers Association
Mal Randall
Non-Executive Director
• Joined the Board in February 2019
• 45+ years extensive experience in corporate, management and
marketing in the resources sector, including 25+ years with the Rio
Tinto group of companies
Guy Robertson
Finance Director
Joint Company Secretary
• Served on the Board of Hastings since October 2012
• 30+ years CFO experience
• CFO for various ASX listed junior mining companies
• Senior finance executive in Jardine Matheson Group in Hong Kong and
Australia including Jardine Lloyd Thompson, Colliers Jardine, and
Franklins Limited
Neil Hackett
Non-Executive Director
Joint Company Secretary
• Joined the Board in November 2018
• 15+ years ASX Director, Company Secretary with mining and industrial
experience
• Corporate Finance and Regulatory Experience with ASIC 1990-1999
• Independent Corporate Governance Advisor and AICD Facilitator
FY23 year in review
|
26
Senior management team
Paul Brown
Chief Executive Officer
• Mining engineer with over 20 years' experience across a range of senior
management and operating roles, most recently as Chief Executive –
Commodities at Mineral Resources Limited
• Expertise covers the entire mining project life cycle and strong track
record in major project construction, management, commissioning and
operation, including at Fortescue Metals Group
Gareth Fleming
Project Director
• Engineering professional with over two decades of experience working
in construction in Australia and overseas
• Experience covers managing and delivering complex projects in
Australia and overseas, including construction of Australia’s largest salt
and potash facility at Mardie for BCI Minerals
Rob Klug
General Counsel
• Resources and corporate lawyer with over 30 years of experience in
start-up and operational environments, including business development
and due diligence
• Most recent positions include general counsel and company secretary
for EV Metals Group and previously as Chief Commercial Officer at
Sandfire Resources
Teck Lim
Chief Financial Officer
• Chartered accountant with 20 years’ accounting and finance
experience, specialising in mining and metals project development at
corporate finance firms KPMG, Deloitte, ING and HSBC
• Formerly CFO at Nico Resources and lead project financial advisor to
Hastings while at KPMG corporate finance. Expertise covers base
metals, bulk commodities, battery minerals and precious metals
Rachael Ward-Pryce
Head of People
• Joined Hastings in April 2021 with nearly two decades of experience in
all facets of human resources management
• Recruited and built teams for domestic and international operations for
Newmont Australia, Resolute Mining, Iluka Resources, Alcoa
Andrea Righetti
GM Project Services
• Joined Hastings with 25 years’ experience in the resources industry,
delivering project controls, contracts and procurement support to
mining and oil and gas projects for EPC/M and owners’ teams
• Most recently General Manager Project Services at Rio Tinto
Tim Gilbert
GM Operations
• Senior mining executive with over 40 years’ experience in the
resources sector across multiple commodities, including battery
metals, base metals, diamonds and gold
• Expertise covers a range of operational and technical roles for
major contractors including Thiess and Leighton, as well as
global mining companies including Rio Tinto
Narelle Marriott
GM Process Development
• Joined Hastings in late 2014 working on metallurgical process
development, bringing experience in operations, flowsheet
development, project engineering, R&D and project improvement
• A minerals process engineer with 20 years’ experience in the mining
industry across nickel, iron ore and rare earths
Hannah Elms
GM Safety, Environment
and Sustainability
• Health and safety professional with over 11 years’ experience in
occupational health and safety management across the mining
industry in lithium, salt and related industries
• Expertise extends to environmental management system
development, integration and implementation
FY23 year in review
|
27
Unique tier 1 asset
World-class deposit with unrivalled high percentage of NdPr:TREO in the orebody in a tier one jurisdiction,
supplying the critical raw materials for rare earth magnets
Average NdPr:TREO Ratio1
Sichuan (China)
NdPr are critical elements
of the global energy
transition
14%
Mt Pass (US)
Kangankunde (Malawi)
16%
LCD / PDP Screens
21%
Bayan Obo (China)
21%
Nolans (NT)
Defence
Headphones
Guidance and control
20%
Ngualla (Tanzania)
Mt Weld (WA)
Speakers
Average
NdPr:TREO ratio
surpassing most
global projects
23%
26%
Songwe Hill (Malawi)
37%
1 Source: Refer to Slide 32
Y
Eu
Sc
33%
Yangibana (WA)
Energy saving
light bulbs
Displays
Y
Y
Ce
Eu
La
Wind turbines
Tb
Ce
Pr
Nd
Pr
Dy
Nd
Electric vehicles
Pr
Nd
Sm
Pm Sm
Light Rare Earths
Tb
Dy
Pr
Eu
Gd
Nd
Gd
Pr
Tb
Dy
Nd
Sm
Ho
Tb
Er
Dy
Smartphone
La
Tm
Ce
Yb
Pr
Nd
Lu
Heavy Rare Earths
FY23 year in review
|
28
Capitalising on high growth market
Fueled by the electrification trend – strong growth in NdFeB sintered magnets for electric vehicles and wind turbines
Anticipated global REO magnet demand growth by industry1
Key drivers for rare earths
216kt
•
Electric drivetrains and wind energy to represent
59% of rare earth oxide demand for magnets by
2032
•
EV demand to grow significantly by 2032 as
governments ban the sale of the traditional internal
combustion engines
•
The Yangibana Project can supply NdPr used in
NdFeB magnets for 1.5 million EVs per year (if
100% of sales to this channel)
•
Wind power has been identified as the fas