Hastings Technology Metals Ltd | ASX:HAS Corporate Presentation May 2026
AUSTRALIA’S
NEXT
INTEGRATED
RARE
EARTHS
PRODUCER.
2
Hastings Snapshot 3
Yangibana REE & Nb Project 4
Thailand MREC Processing Plant 5
Timeline 11
Appendix 16
CONTENTS
3
Yangibana JV Project
› Australia's highest-grade NdPr project
with 37% average NdPr:TREO (up to 52%
in highest-grade areas).
› 20.9Mt Ore Reserve, 17+ year mine life.
› A$160M+ invested in capital
infrastructure. Fully permitted and
shovel-ready.
A mine-to-market rare earths company, with near-term revenue
HASTINGS SNAPSHOT
Near-term Revenue
› Recently acquired 49% interest in a fully
permitted Thai MREC hydromet plant,
targeting first flake production Q4 2026
and generating cash flow.
› HAS share of pre-tax profit: US$10.6M
in Year 1 (indicative).
Mine-to-Market
› Rare earths processing capability
secured and soon to be operational,
creating a processing hub independent
of any single ore source.
› Processing hub designed to accept any
qualifying monazite concentrate,
providing flexibility across multiple ore
sources as production capacity scales
upwards.
Refer Appendix for Ore Reserves and Mineral Resources
Growth & Upside
› Staged capacity ramp targeting 6,000 tpa
initial MREC output, expanding to 12,000
tpa in Year 2 following a planned US$3M
(estimated) expansion funded from Phase
1 operating cash flows.
› Brockman Nb & HREE Project provides
complementary critical minerals exposure
alongside Yangibana's NdPr focus.
› Advanced discussions with oxide
separation customers in the US, Europe
and Asia.
4
AUSTRALIA’S HIGHEST-GRADE
NdPr RARE EARTHS PROJECT
– FULLY PERMITTED, SHOVEL-
READY
Yangibana REE
& Nb Project
20.9Mt
JORC Ore Reserve
37%
Avg NdPr:TREO
A$160M+
Capital Spent To Date
17yr
Mine Life (minimum)
Refer Appendix for Ore Reserves and Mineral Resources
1. Refer Hastings ASX Announcement “Execution of Binding Agreement with Wyloo” dated 16 May 2025
Active Work Program
Yangibana process flow review underway
targeting maximisation of full basket
value across NdPr, niobium and HREE
recovery pathways. Results will inform
construction parameters for an
incoming JV partner, with potential to
further improve overall project
economics.
Luca Giacovazzi (CEO, Wyloo)
"Following significant inbound interest, Wyloo has elected to run a strategic process to sell its 60% interest in the
Yangibana Joint Venture. Thelevel of unsolicited interest that Wyloo has recently received reflects Yangibana's
status as themost progressed rareearth development project in Australia. With a short runway to production
and low capital intensity, this process presents prospectiveacquirers with theopportunity to partner with
Hastings in becoming Australia's next rareearth producer."
Joint Venture (UJV)1
A UJV with HAS and Wyloo, with HAS
retaining a 40% interest of project
revenue and free cash flows. Wyloo
currently running a strategic process to
sell its 60% interest.
5
A CAPITAL-EFFICIENT, NEAR-
TERM REVENUE PATHWAY
Thailand
MREC
Processing
Plant
Refer ASX Announcement “Hastings Acquires Hydromet Plant” dated 31 March
2026
6
Turnkey, Fully Permitted Midstream Solution
THAILAND MREC PROCESSING PLANT OVERVIEW
Location: Kabin Buri, Thailand - 175km from Laem Chabang deep-water port
Facility: Purpose-built Modular hydrometallurgical facility
Capacity:
6,000 tpa initial MREC output capacity, expanding to 12,000 tpa in
Year 2 following a planned US$3M (estimad) expansion, with future
phases targeting up to 36,000 tpa MREC output
Permitting: Existing factory license and EIA approval in place
Output:
Mixed Rare Earth Chloride (MREC) — preferred feed for REO
separation
Feedstock:
Designed for monazite-bearing concentrates, providing flexibility
across multiple ore sources
Refer ASX Announcement “Hastings Acquires Hydromet Plant” dated 31 March 2026
7
Process, output and cost advantages
THAILAND PLANT
Caustic Crack +
Hydrochloric Acid
Sulfuric Acid Roast
Primary
equipment
Multiple Stirred Tank Reactors
(Parallel)
Single Large Rotary Kiln
Feedstock
Flexibility
High: Multiple parallel lines accept
simultaneous inputs from different
sources
Low: Optimised for a single,
consistent concentrate
Redundancy High: Individual reactors can be
serviced without total plant shutdown
Low: Kiln failure or maintenance
stops the entire front-end
Chemical Output Rare Earth Chloride (High Purity) Rare Earth Sulphate / Carbonate
Capital Intensity Low: Modular reactor design, lower
capital cost than kiln-based
equivalents
High: Single large rotary kiln requires
significant upfront capital
25 - 30% Price Premium
MREC chloride flake commands ~27%
premium vs carbonate equivalents
(SMM/Benchmark 2026). Chloride is used by
oxide separators globally.
~4x Lower OPEX vs Remote WA
Competitive Thai energy, labour and reagent costs.
Labour, electricity and reagent costs materially
below Western benchmarks.
8
Enuo Framework Binding Offtake Agreement (FOA)
AFRICAN MONAZITE FEEDSTOCK
Est REE Composition
NdPr (Nd + Pr)
20.0% TREO
Primary magnet elements | EV & wind turbine magnets
DyTb (Dy + Tb)
1.0 – 1.3% TREO
High-temp performance | premium pricing
Product
African Monazite Concentrate
Minimum Grade
≥54% TREO on dry basis (excl thorium)
Annual Volume
Minimum 5,000 tpa feedstock input
Delivery
CIF Laem Chabang Deep-Water Port, Thailand
Term
2 years + 1 year renewal option
First Shipment
Arriving late May 2026 for commissioning and testwork
Price
~US$5,702–6,220/mt (SMM, May 2026)
Key Elements Recovery Rates
NdPr
93% (95% from
monazite / 98%
from MREC)
Dy
91% (95% from
monazite / 96%
from MREC)
Tb
91% (95% from
monazite / 96%
from MREC)
Refer ASX Announcement “Hastings Secures Monazite Feedstock for Thai Hydromet Plant” dated 14 April 2026
9
THAI PLANT ECONOMICS AND DEAL STRUCTURE
UNIT YEAR 1 YEAR 2 YEAR 3
Total MREC Produced tpa 6,000 12,000 12,000
Gross Revenue USD'000 53,400 106,800 106,800
Feedstock, Processing and
Operating Costs
USD'000 (31,500) (62,710) (62,924)
Profit Before Tax (100%) USD'000 21,600 43,790 43,576
Profit Before Tax (HAS 49%) USD'000 10,584 21,457 21,352
Forward-Looking Financial Information: The financial projections set out below are unaudited internal management estimates prepared by the
Company. They are based on a number of assumptions which are subject to uncertainty, and which may not eventuate. Actual production
volumes, revenues, costs, and cashflows may differ materially from those projected. These projections have not been reviewed or audited by an
independent third party. They are provided by management for indicative purposes only and do not constitute a profit forecast or financial
product advice. Investors should not placeunduerelianceon theseprojections.
Note: Phase 2: 5,000 tpa input capacity upgrade assumes a one-off capital cost of US$3M incurred in Year 1 to design, install and commission
additional processing capacity. Installation and commissioning activities occur throughout Year 1, including testing in the latter part of the year.
For conservatism, no incremental production from this additional capacity has been assumed until Year 2. Accordingly, increased production from
Year 2 reflects utilisation of capacity installed in Year 1, with no additional capital expenditure required in Years 2 and 3. Profit before Tax is stated
after depreciation and amortisation of approximately US$0.3M per annum. HAS portion represents 49% of Profits beforeTax.
US$53.4M
Year 1 Gross Revenue (100%)
US$10.6M
Year 1 HAS 49% Pre-Tax Profit
US$21.5M
Year 2 HAS 49% Pre-Tax Profit
Refer ASX Announcement “Hastings Secures Monazite Feedstock for Thai Hydromet Plant” dated 14 April 2026
Refer ASX Announcement “Hastings Reveals Thai Hydromet Plant Flowsheet” dated 22 April 2026
Ownership % 49% of the Thai Plant
Deposit: US$500K upfront deposit
Equity: US$8M in new Hastings shares
Deferred:
US$5.5M cash - production-contingent. No
deferred cash due unless commercial production
achieved
Downside
Protection
Full downside protection on deferred payments
Thailand BOI
Promotion
Applying for BOI promotion during Phase 2:
up to 13-yr Corp Income Tax exemption, import
duty exemptions, and full foreign ownership
rights — materially enhancing post-tax
economics.
Indicative 3-Year Projections (unaudited management estimates) Deal Structure
10
Fiscal & Geopolitical Support
THAILAND ADVANTAGE
Tier-1 Infrastructure
Kabin Buri industrial zone — energy grid,
skilled industrial workforce, established
regional chemical supply chains.
Key Port Logistics
Laem Chabang (Thailand) — no landlocked
rail risk. Established container shipping
routes for feedstock and product.
US-Thailand MOU
Directly supports the US-Thai Critical
Minerals Cooperation MOU (Oct 2025),
positioning HAS in Western government-
backed supply chains.
BOI Fiscal Support
8-13 year CIT exemption, import duty
exemptions on equipment and feedstock,
full foreign ownership rights.
Free Trade Access
Thailand's extensive FTA network positions
MREC exports to Europe and North America
with potential preferential duty treatment.
Near-Term Cash Flow
Secured African monazite feedstock for
commissioning in Q3/Q4 2026 — HAS
generate MREC revenue independent of
Yangibana.
~4x
Lower indicative OPEX
vs remote WA
13yr
BOI Corp Tax
exemption target
175km
From Laem Chabang
deep-water port
2025
US-Thailand Critical
Minerals MOU
Refer ASX Announcement “Hastings Acquires Hydromet Plant” dated 31 March 2026
11
The Road to Revenue: Key Milestones 2026-2028.
TIMELINE & VALUE CATALYSTS
Hastings - from rare earth project development to near-term producer by end 2026
Commenced
technical and
commercial reviews
and funding options
Acquisition of 49%
Interest in Thai MREC
Hydromet Plant
Commenced capital and
operating cost review
Reviewed location
options for Stage 2
Hydromet Plant
Completed Enuo African
Monazite feedstock
Framework Offtake
Agreement
Thai Hydromet Plant
process flow and
economics
June 2026: Legal Close of
Thai Plant Acquisition
Yangibana Process Flow
Review (maximise full
basket value)
Commissioning of Thai
Plant using African
feedstock
Production testing at Thai
Plant
Targeted First MREC
Production and first cash
flow
Q4
CY25
Q1
CY26
Q2
CY26
Q3
CY26
Q4
CY26
12,000 tpa MREC output
capacity to be
commissioned by Q4
2027
Commence 12-month
plant design targeting
36,000 tpa MREC output
capacity - Q4 2027
Envisaged full production
36,000 tpa MREC output
from Q4 2028
H2
CY27
Refer ASX Announcement “Hastings Acquires Hydromet Plant” dated 31 March 2026
Refer ASX Announcement “Hastings Secures Monazite Feedstock for Thai Hydromet Plant” dated 14 April 2026
Refer ASX Announcement “Hastings Reveals Thai Hydromet Plant Flowsheet” dated 22 April 2026
12
SHOVEL-READY,
FULLY PERMITTED
PROJECT
All regulatory
approvals secured.
A$160M+ spent on
capital infrastructure
to date.
SIGNIFICANT
UPSIDE
POTENTIAL
With a permitted
Hydromet Plant as a near-
term production asset
and a fully-permitted,
shovel-ready asset in
Yangibana, Hastings
represents a material re-
rating opportunity.
ESTABLISHED ACCESS
TO GLOBAL OFFTAKE
PARTNERS
Existing MoU & HoA
demonstrate genuine
commercial demand.
TIER-1 ASSET,
WORLD-CLASS
NdPr GRADE
37% NdPr:TREO ratio (up
to 52%) — among the
highest globally.
Yangibana will produce
proportionally more
magnet-critical material
per tonne than almost
any competing deposit.
CONTINUED CRITICAL
MINERALS TAILWINDS
NEAR-TERM
REVENUE — THAI
PLANT
The Thailand MREC plant
creates near-term
revenue pathway (Q4
2026) independent of
Yangibana construction.
13
14
DISCLAIMER
This presentation has been prepared by Hastings Technology Metals Ltd (“Company” or “Hastings”). This presentation is not an offer, invitation, solicitation or other
recommendation with respect to the subscription for, purchase or sale of any securities in the Company. This presentation has been made available for information
purposes only and does not constitute a prospectus, short form prospectus, profile statement or offer information statement nor does it constitute investment or
financial product advice (nor taxation, accounting or legal advice) and it is not intended to be used as a basis for making an investment decision. This presentation is
provided expressly on the basis that you will carry out your own independent inquiries into the matters contained in the presentation and make your own independent
decisions about the affairs, financial position or prospects of the Company. The Company reserves the right to update, amend or supplement the information at any
time in its absolute discretion (without incurring any obligation to do so).
To the maximum extent permitted by law neither the Company, nor its related bodies corporate, officers, their advisers, agents and employees accept any responsibility
or liability to any person or entity as to the accuracy, completeness or reasonableness of the information, statements, opinions or matters (express or implied) arising
out of, contained in or derived from this presentation or provided in connection with it, or any omission from this presentation, nor as to the attainability of any
estimates, forecasts or projections set out in this presentation. Any such responsibility or liability is, to the maximum extent permitted by law, expressly disclaimed and
excluded. Nothing in this material should be construed as either an offer to sell or a solicitation of an offer to buy or sell securities in the United States or any other
jurisdiction where it would be illegal. It does not include all available information and should not be used in isolation as a basis to invest in the Company.
FORWARD LOOKING STATEMENTS
This presentation contains reference to certain intentions, expectations, future plans, strategies and prospects of the Company. Those intentions, expectations, future
plans, strategies and prospects may or may not be achieved. They are based on certain assumptions, which may not be met or on which views may differ and may be
affected by known and unknown risks. The performance and operations of the Company may be influenced by a number of factors, many of which are outside the
control of the Company. No representation or warranty, express or implied, is made by the Company, or any of its directors, officers, employees, advisers or agents that
any intentions, expectations or plans will be achieved either totally or partially or that any particular rate of return will be achieved.
Given the risks and uncertainties that may cause the Company’s actual future results, performance or achievements to be materially different from those expected,
planned or intended, recipients should not place undue reliance on these intentions, expectations, future plans, strategies and prospects. The Company does not
warrant or represent that the actual results, performance or achievements will be as expected, planned or intended. The Company is under no obligation to, nor makes
any undertaking to, update or revise such forward looking statements, but believes they are fair and reasonable at the date of the presentation.
COMPETENT PERSONS’ STATEMENT
The information in this presentation relating to Mineral Resources and Ore Reserves have been prepared by a Competent Person in accordance with the 2012 edition
of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (“JORC Code”) and have been extracted from the release title ‘Annual
Report to shareholders’ dated 30 September 2024 which is available to view at www.asx.com.au under the code “HAS” (the original release). The Company confirms that
it is not aware of any other new information or data that materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. Hastings
confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcements.
The information that relates to Mineral Resources is based on information compiled by David Princep and Lyn Widenbar. Both Mr. Princep and Mr Widenbar are
independent consultants to the Company and members of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr Princep and Mr Widenbar have sufficient
experience relevant to the styles of mineralisation and types of deposits which are covered in this announcement and to the activity which they are undertaking to
qualify as a Competent Person as defined in the JORC Code.
The information that relates to the Ore Reserves at Bald Hill, Simon’s Find, Fraser’s, Auer, Auer North, Yangibana and Yangibana North is based on information reviewed
or work undertaken by Mr. Stephen O’Grady. Mr O’Grady is an independent consultant to the Company and a member of the AusIMM, and a Director of Intermine
Engineering Consultants. Mr O’Grady has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the preparation of
mining studies to qualify as a Competent Person as defined by the JORC Code. Mr O’Grady consents to the inclusion in this announcement of the matters based on his
information in the form and context in which it appears.
The scientific and technical information in this announcement and that relates to process metallurgy is based on information reviewed by Scott Atkinson. Mr Atkinson is
a full-time employee of Hastings Technology Metals Limited and member of the Australasian Institute of Mining and Metallurgy (AusIMM; 3056865) and has sufficient
experience relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as
defined by the JORC Code. Mr Atkinson consents to the inclusion in this announcement of the matters based on their information in the form and context in which it
appears.
The information in this announcement that relates to exploration results in relation to the Yangibana Rare Earths and Niobium Project (“Yangibana Project” or
“Yangibana”) and the Centipede Range Project (“Centipede Project” or “Centipede”) and other exploration results, are based on information compiled by Competent
Person, Dr. Louis Schürmann. Dr. Schürmann is a full-time employee of Hastings and Fellow of the Australasian Institute of Mining and Metallurgy (Aus IMM: 308067). Dr
Schürmann has sufficient experience relevant to the styles of mineralization and types of deposits which are covered in this announcement and to the activity which
they are undertaking to qualify as a Competent Persons as defined in the JORC Code. Dr Schürmann consents to the inclusion of this announcement of the matters
based on the information and context in which it appears. Dr Schürmann has +30 years’ experience as an exploration geologist and project manager.
Refer to Appendix 1 for glossary of defined terms.
15
Hastings Technology Metals Limited
ABN 43 122 911 399
Level 6, 197 St Georges Terrace
Perth Western Australia 6000
T: +61 8 6117 6118
E: info@hastingstechmetals.com
hastingstechmetals.com
Follow us on
Level 3, 5 Mill St
Perth Western Australia 6000
16
16
APPENDIX
17
YANGIBANA PROJECT – RESOURCES AND RESERVES
MINERAL RESOURCES AND ORE RESERVES1
Category mt %TREO %NdPr TREO tonnes
Measured 4.97 0.96 0.37 47,721
Indicated 19.51 0.88 0.32 171,936
Sub-total 24.49 0.90 0.33 219,657
Inferred 5.45 1.05 0.31 57,298
TOTAL 29.93 0.93 0.32 276,955
Deposit mt %TREO %NdPr NdPr: TREO
Bald Hill 8.12 0.79 0.32 41
Fraser’s 1.77 1.01 0.43 43
Simon’s Find 2.69 0.53 0.28 53
Auer 2.83 0.96 0.34 35
Yangibana 1.31 0.79 0.37 47
Yangibana North 4.21 1.29 0.34 26
TOTAL 20.93 0.90 0.33 37
1 Refer ASX Announcement 6 February 2023 “Yangibana Ore Reserves Increase by 25%”; numbers may not add due to rounding; for reference that the Ore Reserves stated is included as part of the Mineral Resources. Other prospects of 1.82Mt not included in the individual prospects section.
2 Refer ASX Announcement 4 September 2024 “Maiden Niobium Measured and Indicated Mineral Resource at the Yangibana Rare Earth and Niobium Project”
Disclaimer: There is no certainty that further exploration work will result in the determination of Mineral Resources (or Ore Reserves).
Category mt %TREO %NdPr NdPr: TREO
Proved 4.89 0.95 0.37 39
Probable 16.03 0.88 0.32 36
TOTAL 20.93 0.90 0.33 37
INDIVIDUAL DEPOSITS (at Yangibana)
NIOBIUM RESOURCES (at Yangibana)
Simon’s Find
Category mt %TREO %NdPr TREO tonnes
Measured - - - -
Indicated 3.14 0.52 0.27 16,206
Sub-total 3.14 0.52 0.27 16,206
Inferred 0.05 0.06 0.31 295
TOTAL 3.19 0.52 0.27 16,501
Bald Hill
Category mt %TREO %NdPr TREO tonnes
Measured 3.55 0.82 0.34 29,136
Indicated 5.23 0.75 0.30 39,290
Sub-total 8.79 0.78 0.31 68,425
Inferred 1.17 0.67 0.27 7,787
TOTAL 9.96 0.77 0.31 76,212
Fraser’s
Category mt %TREO %NdPr TREO tonnes
Measured 0.75 1.25 0.53 9,407
Indicated 1.47 0.75 0.32 11,001
Sub-total 2.23 0.92 0.39 20,408
Inferred 0.01 0.60 0.25 44
TOTAL 2.24 0.91 0.39 20,452
Auer
Category mt %TREO %NdPr TREO tonnes
Measured - - - -
Indicated 3.54 0.93 0.32 32,796
Sub-total 3.54 0.93 0.32 32,796
Inferred 1.10 0.76 0.24 8,297
TOTAL 4.64 0.89 0.30 41,093
TOTAL JORC (2012) ORE RESERVES BY CATERGORY AND DEPOSIT (6 FEBRUARY 2023)
Yangibana
Category mt %TREO %NdPr TREO tonnes
Measured - - - -
Indicated 1.98 0.71 0.34 14,034
Sub-total 1.98 0.71 0.34 14,034
Inferred 0.33 0.64 0.31 2,146
TOTAL 2.31 0.70 0.33 16,180
Yangibana North
Category mt %TREO %NdPr TREO tonnes
Measured 0.66 1.39 0.36 9,179
Indicated 4.15 1.41 0.36 58,609
Sub-total 4.81 1.41 0.36 67,788
Inferred 0.97 1.43 0.37 13,914
TOTAL 5.78 1.41 0.36 81,702
Category mt Nb2O5 ppm Nb2O5 tonnes
Measured 2.37 1,035 2,251
Indicated 4.36 2,995 13,050
Sub-total 6.73 2,305 15,501
Inferred 0.01 1,435 20
TOTAL 6.74 2,305 15,521
TOTAL JORC (2012) MINERAL RESOURCES (30 OCTOBER 2022)
18
PEER COMPARISON – NDPR:TREO RATIO
Mine
Majority / Full
Ownership
Ticker
Stage of
Development
Capex (A$m)
Ore Reserves
(Proved)
Mt
Ore Reserves
(Proved)
Grade –
NdPr / TREO
Ore Reserves
(Probable)
Mt
Ore Reserves
(Probable)
Grade
NdPr/TREO
Ore Reserves
(Total)
Mt
Ore Reserves
(Total)
Grade
NdPr/TREO
NdPr:TREO
ratio1
(Total Ore
Reserves)
Source
Yangibana
Hastings Technology
Metals Ltd
HAS:ASX Pre-production 474 4.89 0.37 / 0.95% 16.03 0.32 / 0.88% 20.93 0.33 / 0.90% 37%
6 February 2023: ASX Announcement: “Yangibana Ore Reserves
Increase by 25%”
Nolans Arafura Rare Earths Ltd ARU:ASX Pre-production
1,886
(US$1,226m)
5 0.791 / 3.00% 24.6 0.741 / 2.80% 29.50 0.771
/ 2.90% 26%
11 November 2022: ASX Announcement: "Nolans Project
Update"
23 July 2024: ASX Announcement: "Arafura achieves major debt
funding milestone"
Mt Weld Lynas Rare Earths Ltd LYC:ASX Production N/A 21.2 1.72 / 7.40% 10.8 1.06 / 4.50% 32.0 1.50 / 6.42% 23%
5 August 2024: ASX Announcement: “Mineral Resources and
Ore Reserve Update”
Bayan Obo2
China Northern Rare
Earth Group High-Tech
Co Ltd
600111:CH Production N/A - - - - 48 1.261
/ 6% 21%
September 2021: Dating of monazite-apatite-allanite-epidote
corona from the Bayan Obo Group in the northern margin of the
North China Craton: implications for the time of regional Au and
REE mineralization
4-7 September 2014: 1st
European Rare Earth Conference,
“China’s Rare Earth Ore Deposits and Beneficiation Techniques”
refer table 2
Ngualla
Peak Rare Earths
Limited
PEK:ASX
FEED
Completed
441 17.0 1.021
/ 4.78% 1.5 1.081
/ 5.10% 18.5 1.07 / 4.80% 21%
24 October 2022: ASX Announcement: “Ngualla Rare Earths
Project Completion of Bankable Feasibility Study Update”
30 November 2023: ASX Announcement: “Completion of FEED
Study”
Songwe Hill Mkango Resources Ltd MKA:TSXV Feasibility
479
(US$311m)
8.16 0.26 / 1.28% 9.99 0.21 / 1.07% 18.15 0.24 / 1.16% 20%
19 August 2022: SEDAR Announcement: “Technical report (NI-
43-101) Mkango”
Kangankunde
Lindian Resources
Limited
LIN:ASX Feasibility
A$60m
(US$40m)
- - 23.7 0.571/ 2.9% 23.7 0.571/ 2.9% 20%
1 July 2024: ASX Announcement: “Kangankunde Project Stage 1
Outstanding Feasibility Study Results”
Mountain Pass MP Materials Corp MP:NYSE Production N/A 0.583
0.671
/ 4.28% 25.233
0.981
/ 6.25% 25.813
0.971
/ 6.20% 16% 28 February 2024: SEC Filing: Form 10-K – Annual Report
YANGIBANA PROJECT – PEER COMPARISON
Notes:
1Calculated from available information i.e. NdPR/TREO ratio when provided converted to NdPr % (grade)
2 Bayan Obo is a Chinese Ore Reserve estimate and doesn’t have Proved and Probable estimates. The Ore Reserve estimate (Total) was obtained from a geological research paper
3 Mountain Pass has been converted from US short-tons to metric tonnes
Capital Costs in US Dollars converted at 0.65 AUD/USD exchange rate.
19
World-Class NdPr Grade
YANGIBANA RESOURCE & RESERVE SUMMARY
Category Tonnes TREO % NdPr:TREO
JORC Mineral Resource 29.9 Mt 0.93% 37% avg LOM
Updated MRE (Feb 2024) 21.0 Mt 1.12% up to 52%
JORC Ore Reserve 20.9 Mt 0.90% 0.33% NdPr
Mine Life 17+ years — —
20
26
22
37
52
0
10
20
30
40
50
60
Industry
Average
Mount
Weld
Arafura
Nolan
Yangibana
(avg)
Yangibana
(peak)
Yangibana's 37-52% NdPr:TREO ratio is ~2x the global average,
producing proportionally more magnet-critical material per tonne.
NdPr:TREO Grade Comparison
0 1 2 3 4 5
KILOMETRE
S
Existing 29.93mt Mineral Resource has
been defined over 24km of strike length
Additional exploration potential strike
length of 42km identified
1. Refer slide 17 for ore Reserves and Mineral Resources & Slide 30 for Source data
Disclaimer: There is no certaintythat further exploration work will result in the determination of Mineral Resources (or Ore Reserves).
Cautionary Statement: The Exploration Target has been prepared and reported in accordance with the 2012 edition of the JORC Code. The potential quantity and grade of the
Exploration Target is conceptual in nature. There has been insufficient exploration to estimate a Mineral Resource for all target areas reported. It is uncertain if further
exploration will result in the estimation of a Mineral Resource.
Competent Person Statement: The information in this announcement that relates to exploration results in relation to the Yangibana Rare Earths and Niobium Project
(“Yangibana Project” or “Yangibana”) and the Centipede Range Project (“Centipede Project” or “Centipede”) and other exploration results, are based on information compiled
by Competent Person, Dr. Louis Schürmann. Dr. Schürmann is a full-time employee of Hastings and Fellowof the Australasian Institute of Mining and Metallurgy (Aus IMM:
308067). Dr Schürmann has sufficient experience relevant to the styles of mineralization and types of deposits which are covered in this announcement and to the activity
which they are undertaking to qualify as a Competent Persons as defined in the JORC Code. Dr Schürmann consents to the inclusion of this announcement of the matters based
on the information and context in which it appears. Dr Schürmann has +30 years’ experience as an exploration geologist and project manager.
20
Demand
• Price recovery underway with NdPr prices up ~20% since a low in June 2024. Significant deficit to start
growing from 2026 onwards coinciding with first concentrate from Yangibana in 2028 is well-timed to
meet demand surge
• Demand for NdPr oxides expected to increase by ~80% over the next decade (from 2026), fueled
predominantly by growth in E-mobility, humanoid robotics and wind turbines.
77
141
200
247
47
58
63
63
39
42
46
50
14
24
25
28
38
55
57
59
0
50
100
150
200
250
300
350
400
450
500
2025 2030 2035 2040
Electric Vehicles Consumer Electronics Industrial Wind Energy Other
Magnet demand drives projected supply deficit
SUPPLY & DEMAND –DRIVEN BY MAGNETS DEMAND
CAGR
2025-2040
18.12%
4.27%
3.61%
10.41%
6.49%
CAGR
+11.02%
p.a.
NdFeB high performance magnet consumption1 by user category in 1.000mt
1 Benchmark Intelligence, Wood Mackenzie , CRUand Hastings Analysis
2 Boston Consulting Analysis 2024
3 Coherent Market Insights 2024
0
20
40
60
80
100
120
140
160
180
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
Supply Deficit Supply Demand
NdPr market balance - (kt NdPr oxide), 2020-20401
Supply
• Long project development lead times raise questions around ability of new mines in permitting,
financing and supply ramp up
• CRU forecast supply gap to 2030 represents around 8x Yangibana’s NdPr oxides
production of 3.4ktpa
• Worldwide NdPr supply is projected to grow at a CAGR of 5.3% from 2022 to 20301. However, this
growth significantly lags behind the increasing demand for rare earths in permanent magnets,
highlighting a critical supply-demand gap.
23% Supply Deficit
(8x Yangibana)
39% Supply
Deficit
(18x
Yangibana)
216
321
391
447
kt
21
Mixed Rare Earth Chloride (MREC) Production.
THAI PLANT – THE HYDROMET PROCESS
Refer ASX Announcement “Hastings Acquires Hydromet Plant” dated 31 March 2026
Refer ASX Announcement “Hastings Reveals Thai Hydromet Plant Flowsheet” dated 22 April 2026
22
Technical Services & Operational Partner
ENUO HOLDINGS
Services Agreement
Signed Jan 2026. Enuo to undertake
metallurgical/beneficiation test work to
optimize Yangibana and Brockman ore .
Niobium Recovery
Nb = ~15% of Yangibana's total economic
value. Enuo to evaluate recovery pathways
and optimal product routes.
Specialist Expertise
Enuo brings deep experience in monazite
processing and solvent extraction across
facilities in Africa, China and Japan.
Integrated Flowsheet
Insights from Yangibana directly
transferable to Brockman. Shared, capital-
efficient metallurgical results serves to
benefit both projects.
Independent Feedstock
Secures 3rd-party African monazite to
commission/operate Thai plant in Q3/Q4
2026 —independent of Yangibana.
Broadened Product Slate
Full basket assessment: NdPr + Nb + Zr +
HREE. Potential to materially improve overall
project economics beyond NdPr.
Thai Plant Operations
Oversight of day-to-day operations at the
Kabin Buri facility, providing on-
Share your feedback