Yangibana Project Funding Update
Released
Released
Announcement PDF
22 November 2023
YANGIBANA PROJECT FUNDING UPDATE
HIGHLIGHTS
•
At-the-Market equity financing facility for up to $50 million established with Alpha Investment
Partners (“AIP”) to provide working capital funding flexibility as project financing process is advanced
•
Project financing process for Yangibana Rare Earths Project (“Yangibana Project”) advancing through
first stage financiers’ investment and credit committee approvals
•
Multiple non-binding financing proposals received from global mining funds and debt capital market
investors to fund the Yangibana Project debt size in the order of the target gearing ratio of 60%1
•
Discussions ongoing with Federal Government, following recent announcement of $2 billion
expansion in critical minerals financing
•
Strategic partner and joint venture indicative proposals received from global mining funds
•
Certification of Green Financing Framework to enable issue of green finance instruments, accredited
by Second Party Opinion (“SPO”) provider, Det Norske Veritas (“DNV”) Business Assurance Australia
•
Next steps include shortlisting preferred financier(s)/syndicated lender group to conduct final due
diligence, long form term sheet, intercreditor terms (if required) and site visits.
Australia’s next rare earths producer, Hastings Technology Metals Ltd (ASX: HAS) (“Hastings” or “the
Company”) is pleased to provide an update on the project financing process for the Yangibana Project.
During the September quarter, Hastings completed early infrastructure works at the Yangibana Project,
including the Kurrbili Accommodation Village, Yangibana Airstrip, access roads, production borefields,
water pipelines and clearing and grubbing of the entire plant site.
HASTING ESTABLISHES AT-THE-MARKET EQUITY FACILITY
The At-the-Market facility with AIP represents a strategic equity financing option for up to A$50 million,
offering the Company the flexibility to raise capital incrementally over a four-year period at an issue
price referable to prevailing market prices, subject to a floor price that is set by Hastings.
Hastings retains full control over all major aspects of the placement process, having sole discretion as
to whether to use the facility, the number of shares to be issued, and the minimum issue price of any
issued shares. The final issue price will be calculated as the greater of a floor price set by Hastings in the
drawdown notice and a volume weighted average price over a period of Hastings’ choosing (at the sole
discretion of Hastings) less a discount of five per cent. The facility establishment fee is A$25,000.
Furthermore, the At-the-Market facility will not impose restrictive conditions, preserving the Company’s
operational and capital raising freedom. This makes At-the-Market facilities a compelling option for
Hastings, aligning with the Company’s long-term growth strategy and commitment to maximising
shareholder value.
As collateral for the At-the-Market facility, Hastings will issue 6.5 million shares to AIP from its LR 7.1
capacity, leaving a balance of 12.9 million capacity under LR 7.1. Any placements under the facility in
excess of Hastings’ LR 7.1 capacity will require shareholder approval.
This standby equity capital facility aligns with Hastings' commitment to prudent financial management,
facilitating a controlled approach to capital raising, and minimising shareholder dilution. The facility can
be terminated by Hastings at any time without penalty to the Company.
PROJECT FINANCING
Hastings has completed the first stage of the project financing process following the release of its staged
development feasibility study, including first stage financiers’ investment and credit committee
approvals. This has culminated in the Company receiving non-binding indicative financing proposals1
from multiple parties, including from global mining funds, senior debt and fixed income investors (debt
capital markets), to fund the Yangibana Project in the order of the target gearing ratio of 60% of the total
funding package2 .
This is in addition to the previously announced financing support from commercial banks and
government agencies3.
The receipt of the financing proposals follows completion of lenders due diligence reports, including an
independent technical expert report from Behre Dolbear Australia (“BDA”), which confirmed that the
Yangibana Project’s revised capital and operating cost estimates and project delivery structure and
schedule are reasonable and appropriate for a project of this nature.
Additionally, Hastings has received various strategic partner and joint venture proposals from global
mining funds which would reduce funding requirements, as well as enable the Company to leverage
synergies, share risks, and access additional resources and expertise of a partner.
With the receipt of multiple financing proposals including loans, bonds, and joint venture proposals,
Hastings is now in the process of negotiations to secure the most optimal financing package and
syndicate that enhances long term value creation for shareholders. Hastings is working with its financial
advisors and consultants, to shortlist preferred financiers/syndicated lender group to conduct final due
diligence and site visits, with final submissions due shortly thereafter.
Commenting on the funding progress, Executive Chairman, Mr Charles Lew, said:
“Securing multiple indicative funding proposals is a significant milestone. We are pleased by the strong
response we have received from various potential financiers validating the economic and technical viability of
the Yangibana Project.
“As we evaluate each option, we are focused on choosing the path that best aligns with our strategic objectives
and drives the best economics for the business. As we work towards finalising the funding stack, we will
continue to look at opportunities to optimise our working capital and operating efficiencies to deliver value for
our shareholders.”
Disclaimer: There are no guarantees that the indicative proposals will result in approved project funding
Refer to ASX Release ‘Quarterly Activities Report (for the period ended 30 September 2023)’
3
See ASX Release ‘Quarterly Activities Report (for the period ended 30 June 2023)’, dated 17 July 2023, ‘NAIF increases financial support for
Yangibana Rare Earths Project to A$220 million’, dated 17 January 2023, ‘Letter of Support secured from Export Finance Australia for
$100m loan’, dated 21 March 2023
1
2
GREEN FINANCE FRAMEWORK
In recognition of the strong ESG credentials of the Yangibana Project, Hastings has established a Green
Financing Framework under which the Company may issue Green Loans or Green Bonds (hereafter
referred to as “Sustainable Finance”). DNV has issued a SPO confirming the Framework’s alignment with
the International Capital Market Association’s Green Bond Principles (“GPBs”) and the Loan Market
Association’s Green Loan Principles.
The rare earth concentrate produced from the Yangibana Project will realise significant environmental
benefits as critical inputs for electrification and renewable energy technologies, aligning with the GBP
categories of clean transportation, renewable energy and energy efficiency. The Yangibana Project’s
operations will also meet other categories including sustainable water and wastewater management.
The Company’s ESG credentials are aligned with the United Nations Sustainability Development Goals
(“UNSDGs”) as a signatory of the UN Global Company, and advances four UNSDGs relevant to the GBPs,
including SDG 6 (Clean Water and Sanitation), SDG 7 (Affordable and Clean Energy), SDG 8 (Decent Work
and Economic Growth) and SDG 9 (Industry, Innovation and Infrastructure).
Authorised by the Board for release to the ASX.
FOR FURTHER INFORMATION CONTACT:
Charles Lew
Executive Chairman
+65 62209220
MEDIA ENQUIRIES:
Stephanie Vanicek
Communications Manager
+61 405 183 237
Paul Brown
Chief Executive Officer
+61 8 6117 8605
Teck Lim
Chief Financial Officer
+61 8 6117 6118
ABOUT HASTINGS TECHNOLOGY METALS LIMITED
Hastings Technology Metals Limited is a Perth-based rare earths company primed to become the world’s
next producer of neodymium and praseodymium concentrate (“NdPr”). NdPr are vital components in
the manufacture of permanent magnets used every day in advanced technology products ranging from
electric vehicles to wind turbines, robotics, medical applications, and digital devices.
Hastings’ flagship Yangibana Rare Earths Project located in the Gascoyne and Pilbara regions of Western
Australia, contains one of the most highly valued NdPr deposits in the world with NdPr to Total Rare
Earth Oxide ratio of up to 52% in some areas of the orebody.
The Yangibana Project will be developed in two stages with an initial focus on the construction of the
Yangibana mine and beneficiation plant to produce 37,000 tonnes per annum of mixed rare earth
concentrate, followed by the construction of a hydrometallurgical plant in Onslow with the capacity to
process 15,000 tonnes per annum of Mixed Rare Earth Carbonate*. The Yangibana Project is permitted
for long-life production and with offtake commitments and debt finance being finalised.
Hastings holds a strategic 20.4% shareholding in TSX-listed Neo Performance Materials, a leading global
rare earth processing and advanced permanent magnets producer, providing the Company with the
opportunity to explore opportunities to create a mine-to-magnet supply chain.
Hastings also owns and operates the Brockman project, Australia’s largest heavy rare earths deposit,
near Halls Creek in the Kimberley.
For more information, please visit www.hastingstechmetals.com
*See ASX announcement 6 February 2023. The Company is not aware of any new information or data
that materially affects the information included in the 6 February 2023 announcement and all material
assumptions and technical parameters underpinning the production target in the relevant market
announcement continues to apply and has not materially changed.