HIGHLIGHTS
•
Reduction in Total Recordable Injury Frequency Rate (“TRIFR”) to 2.31, with no recordable injuries
for the period
•
Five years lost time injury free marked during the quarter, demonstrating ongoing commitment to
health and safety
•
Appointment of experienced mining executive, Mr Paul Brown, as Chief Executive Officer
•
Completion of early works including the aerodrome, village, access roads, production bore fields,
water pipeline and clearing and grubbing of the of the entire plant site
•
Completion of the $210 million Engineering, Procurement and Construction (“EPC”) contract with
GR Engineering Services (“GRES”)
•
Expansion of the offtake contract with thyssenkrupp Materials Trading (“thyssenkrupp”) to include
up to two-thirds of Stage 1 concentrate from the Yangibana Rare Earths Project (“Yangibana
Project”), in addition to mixed rare earth carbonate (“MREC”), to meet bankability requirements
•
Completion of independent due diligence reports following the release of the staged development
feasibility study, including a technical review by lenders’ Independent Technical Expert, Behre
Dolbear Australia (“BDA”)
•
Advancement of debt funding process with indicative commitments and term sheets received from
multiple financiers
•
Completion of the five-year review of the Yangibana Rare Earths Project Agreement (“Project
Agreement”) with the Thiin-mah, Warriyangka, Tharrkari and Jiwarli (“TMWTJ”) People
•
Hastings had $67.5 million in cash and equivalents as of 30 September 2023
Commenting on the September 2023 quarter, Hastings’ Chief Executive Officer, Mr Paul Brown, said:
“Since joining Hastings during the quarter, I have been impressed by the level of advancement of the
Yangibana Project in preparation for full construction. Having an operating village, airstrip and borefield
provides a strong base from where we can ramp-up our workforce and operational activities as we move
into 2024.
“Alongside our significant investment to date at site, we are building our internal processes and
capabilities to support the move into project development. This includes across safety, environment,
procurement, and human resources.”
“We are focused on finalising the optimal funding stack for Stage 1 of the Yangibana Project. This
includes a flexible debt package that will drive the best economics for our shareholders, while also
looking at opportunities to continue reducing the equity component by maintaining a razor-sharp focus
on identifying cost savings and ongoing efficiencies.”
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 1 of 9
Australia’s next rare earths producer, Hastings Technology Metals Ltd (ASX: HAS) (“Hastings” or “the
Company”), is pleased to report on development, corporate and exploration activities for the threemonth period to 30 September 2023. Activity focused mainly on advancing construction of the
Yangibana Project in the Gascoyne region and planning for a proposed hydrometallurgical plant in the
Pilbara region of Western Australia.
SUSTAINABILITY
Health and Safety
Health and safety remains a key focus for the Company with no recordable injuries reported during the
quarter and the TRIFR reducing by 37% to 2.31, compared to the prior corresponding period. During the
quarter, Hastings also marked five years with zero lost time injuries at the Yangibana Project.
Native Title and Heritage
Subsequent to 30 September 2023, Hastings and the TMWTJ People completed the five-year review of
the Project Agreement signed in 2017. The Implementation Committee, established in FY23 to oversee
the review, met on-country and reaffirmed their mutual commitment to working collaboratively to
develop the Yangibana Project.
The review included discussions around employment, training, and business opportunities as well as a
review of appropriate goals and targets and included a visit to heritage sites around Yangibana with
TMWTJ Senior Elder Peter Salmon.
Hastings has worked closely with the TMWTJ People since 2017 to co-design the Yangibana Project with
cultural consideration in mind, and to protect important heritage sites.
Figure 1 TMWTJ Senior Elder Peter Salmon visiting Yangibana site
Figure 2 Implementation Committee Chair Brendon Thompson and
Hastings GM Corporate Affairs Vince Catania
Environmental, Social and Governance (“ESG”)
During the quarter, Hastings began implementing plans to reduce plastic waste at the Yangibana Project
mine site. This included the scheduled installation of washing basins to facilitate the use of good-quality
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 2 of 9
reusable containers that will be issued to permanent team members and long-term contractors. In the
interim, compostable packaging will be provided for crib lunches.
Other ESG activities progressed during the quarter included:
•
Ongoing engagement with local governments and communities, including meetings with the
Shire of Carnarvon and Shire of Upper Gascoyne to provide project updates and facilitating a
site visit by the Board of Regional Development Australia Midwest and Gascoyne
•
Ongoing work to clean-up and rehabilitate the location of the Yangibana Project’s fly camp,
including excavation of redundant buried services, removal of bulk waste items and levelling of
redundant windrows
•
Following the successful completion of the five-year review of the Project Agreement with the
TMWTJ People, the Yangibana Project remains fully permitted for development to commence.
YANGIBANA PROJECT DEVELOPMENT
Development Activities
Early infrastructure work on non-processing infrastructure at the Yangibana mine site was finalised
during the quarter, ahead of the mobilisation of GRES for construction of the beneficiation plant.
This included the practical completion of Kurrbili Accommodation Village, including 294 rooms, kitchen,
messing facilities, medical centre, administration buildings, sports courts, and landscaping. Airport
facilities at the Yangibana Airstrip were also completed.
As at 30 September 2023, $126 million has been invested in early works at Yangibana.
Figure 3 Kurrbili Accommodation Village
Figure 4 Yangibana Airstrip - Airport Facilities
Contracts and Procurement
During the period, the long form EPC contract was signed with GRES for the delivery of the beneficiation
plant and associated infrastructure. Under the $210 million contract, GRES will design and construct the
Yangibana Project’s beneficiation plant and all associated infrastructure, including engineering,
manufacture, supply, installation, dry and wet commissioning, and testing of the facility over a period
of 18 months.
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 3 of 9
GRES continues to work with Hastings on engineering and procurement under an early works
agreement until it mobilises to site. Engineering designs for the Yangibana Project’s beneficiation plant
is at 74% complete, with the next key deliverables to be the finalisation of detailed design for the bulk
earthworks, civil and structural elements.
Long-lead equipment for the Yangibana Project received during the quarter included the trommel
frame, main bearing lube system and discharge end head and trunnion for the SAG mill, as well as the
girth gear, slurry and froth pumps and cooling tower.
CORPORATE
Management Team Update
In September, experienced mining executive, Mr Paul Brown, commenced as Chief Executive Officer
bringing a strong track record built over two decades in various senior roles in the resources sector,
including the delivery and operation of several significant mining projects.
Most recently, Mr Brown spent eight years at Mineral Resources Limited (“MinRes”), where he was
Chief Executive – Commodities and also held the position of Chief Executive – Lithium.
Prior to joining MinRes, Mr Brown’s career spanned general management, operational leadership,
technical direction, project and studies management, business enhancement, mineral resource
assessment, and mine strategy, including at Leighton Holdings, HWE Mining and Fortescue Metals
Group.
The Company has promoted Mr Tim Gilbert to its Executive Leadership Team as Executive General
Manager Mining Operations, with oversight of operations, operational readiness, health and safety,
environmental approvals, and exploration.
With over three decades of experience across a range of strategic, operational, and technical roles in
the resources sector, including as GM Operations for Covalent Lithium, Mr Gilbert will be critical to
ensuring the business is ready for the project’s critical commissioning phase.
Offtake arrangements
In September, Hastings and thyssenkrupp announced that both parties had agreed to expand the terms
of the offtake contract signed in April 2021 to include up to two-thirds of Stage 1 rare earth concentrate
from the Yangibana Project in addition to MREC. The offtake terms will satisfy the Yangibana Project’s
debt financing and bankability requirements, underpinning the optimal funding structure.
The expanded offtake is aligned with the two-stage development strategy for the Yangibana Project,
with the remaining one-third of production output during the first five years not under thyssenkrupp
offtake available to Hastings to maximise value through spot sales or other commercial arrangements.
Hastings remains engaged in discussions with a range of customers, with strong interest in the
Company’s products as downstream producers look to secure supplies of rare earth feedstock in
anticipation of the growing supply deficit this decade.
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 4 of 9
Quarterly Expenditure
During the quarter, the Company had cash outflows on exploration and evaluation costs of
approximately $0.9 million. $257,000 was paid in respect of directors’ fees, salaries, and consulting fees.
Cash outflows for project development during the quarter was $32.7 million.
Project Funding
Following the release of the staged development feasibility study at the end of May, Hastings has
completed refreshed independent due diligence reports, including a technical review of the Yangibana
Project by BDA – the lenders’ Independent Technical Expert. BDA has considered that cost estimations
to be reasonable and appropriate.
A refreshed market consultant report by CRU has also verified the Yangibana Project’s competitive
position on the first quartile of the global margin curve, confirming that Hastings will be one of the
highest margin producers of rare earths globally.
Hastings is assessing indicative commitments and indicative term sheets from multiple financiers for up
to 60% gearing for Stage 1 of the Yangibana Project.
During the quarter, the Company also successfully completed the external audit of its financial
statements with external auditors, PwC Australia.
This report has been approved by the Board for release to the ASX.
FOR FURTHER INFORMATION CONTACT:
Paul Brown
Chief Executive Officer
+61 8 6117 6118
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
MEDIA QUERIES:
Stephanie Vanicek
Communications Manager
+61 405 183 237
Page 5 of 9
ABOUT HASTINGS TECHNOLOGY METALS LIMITED
Hastings is a Perth based rare earths company primed to become the world’s next producer of
neodymium and praseodymium concentrate (“NdPr”). NdPr are vital components in the manufacture
of permanent magnets used every day in advanced technology products ranging from electric vehicles
to wind turbines, robotics, medical applications and digital devices.
Hastings’ flagship Yangibana Project located in the Gascoyne and Pilbara regions of Western Australia,
contains one of the most highly valued NdPr deposits in the world with a NdPr to Total Rare Earth Oxide
ratio of up to 52% in some areas of the orebody.
The Yangibana Project will be developed in two stages with an initial focus on the construction of the
mine and beneficiation plant to produce 37,000 tonnes per annum of mixed rare earth concentrate,
followed by the construction of a hydrometallurgical plant with the capacity to process 15,000 tonnes
per annum of mixed rare earth carbonate. The Yangibana Project is permitted for long-life production
and with offtake commitments and debt finance being finalised.
Furthermore, Hastings has a 20.39% strategic shareholding in TSX-listed Neo Performance Materials, a
leading global rare earth processing and advanced permanent magnets producer, providing the
Company with the opportunity to explore opportunities to create a mine-to-magnet supply chain.
Hastings also owns and operates the Brockman Project, Australia’s largest heavy rare earths deposit,
near Halls Creek in the Kimberley.
For more information, please visit www.hastingstechmetals.com
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 6 of 9
COMPETENT PERSONS AND QUALIFYING PERSONS STATEMENT
The information that relates to the Ore Reserves at Bald Hill, Fraser’s, Yangibana, Auer and Auer North
and Yangibana North is based on information reviewed or work undertaken by Mr Stephen O’Grady
(AusIMM), a Director of Intermine Engineering Consultants. Mr O’Grady has sufficient experience
relevant to the style of mineralisation and type of deposit under consideration and to the preparation
of mining studies to qualify as a Competent Person as defined by the 2012 edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (“JORC Code 2012”).
Mr O’Grady consents to the inclusion in this announcement of the matters based on his information in
the form and context in which it appears. The scientific and technical information that relates to process
metallurgy is based on information reviewed by Ms. Narelle Marriott (General Manager – Process
Development). Ms Marriott is an employee of the Company and a member of the AusIMM. She has
sufficient experience relevant to the style of mineralisation and type of deposit under consideration and
to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code 2012.
Ms Marriott consents to the inclusion in this announcement of the matters based on their information
in the form and context in which it appears.
The information that relates to Mineral Resources at the Yangibana Project and the Brockman Project
is based on information compiled by Mr David Princep of Gill Lane Consulting, who is a Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM). Mr Princep is a consultant to Hastings and
has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity which they are undertaking to qualify as a Competent Person as
defined in the JORC Code 2012. Mr Princep consents to the inclusion in this report of the matters based
on their information in the form and context in which it appears.
The information that relates to Exploration Results is based on information reviewed and compiled by
Louis Schürmann. Dr Schürmann is an employee of the Group and a Fellow of the Australian Institute of
Mining and Metallurgy (FAusIMM). Dr Schürmann has sufficient experience relevant to the styles of
mineralisation and types of deposits which are covered in this report and to the activity which he is
undertaking to qualify as a Competent Person as defined in the JORC Code 2012. Dr Schürmann consents
to the inclusion in this report of the matters based on his information in the form and context in which
it appears.
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Page 7 of 9
APPENDIX – MINING TENEMENTS HELD AS AT 30 SEPTEMBER 2023
YANGIBANA PROJECT
Gascoyne Metals Pty Ltd (70%) /
Yangibana Pty Ltd (30%)
Tenement
Locality
Status
E09/2296
WA
Live
E09/2298
WA
Live
E09/1703
WA
Live
E09/1704
WA
Live
E09/1705
WA
Live
E09/1706
WA
Live
E09/2333
WA
Live
M09/0159
WA
Live
M09/0161
WA
Live
M09/0163
WA
Live
G09/0011
WA
Live
G09/0013
WA
Live
Yangibana Pty Ltd (100% subsidiary)
Tenement
G09/0017
G09/0018
G09/0020
G09/0021
G09/0022
G09/0026
G09/0027
G09/0028
L09/0093
L09/0095
L09/0096
L09/0097
M09/0158
M09/0162
M09/0176
M09/0178
E09/1700
E09/1943
E09/1944
E09/2018
Locality
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
Status
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Ark Gold Pty Ltd (100% subsidiary)
Tenement
E09/2385
E09/2399
Locality
WA
WA
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Status
Live
Live
Gascoyne Metals Pty Ltd (100% subsidiary)
Tenement
E09/1989
E09/2007
E09/2084
E09/2086
E09/2095
E09/2129
E09/2137
E09/2334
E09/2364
E09/2403
E09/2404
G09/0010
G09/0014
G09/0023
G09/0024
G09/0025
L09/0066
L09/0067
L09/0068
L09/0069
L09/0070
L09/0071
L09/0072
L09/0074
L09/0075
L09/0080
L09/0081
L09/0082
L09/0083
L09/0085
L09/0086
L09/0087
L09/0089
L09/0091
M09/0157
M09/0160
M09/0164
M09/0165
M09/0177
M09/0179
P09/0489
Locality
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
WA
Status
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Live
Page 8 of 9
BROCKMAN PROJECT
Brockman Project Holdings Pty Ltd
(100% subsidiary)
Tenement
Locality
Status
E80/5248
WA
Lodged
HASTINGS TECHNOLOGY METALS LIMITED
Level 6, 197 St Georges Terrace, Perth WA 6000
www.hastingstechmetals.com | +61 8 6117 6118
Brockman Project Holdings Pty Ltd
(100% subsidiary)
Tenement
Locality
Status
P80/1626
WA
Live
P80/1628
WA
Live
P80/1629
WA
Live
P80/1630
WA
Live
Page 9 of 9
Share your feedback
Discover